Adjudicating Officer order (Form N)
20/2023
Parties involved
- Complainant
- H. Prasannaah
- Respondent
- VGN Property Developers Pvt. Ltd.,
Hearings of this complaint (listed on 11 days)
-
19 Mar 2025 Case diary, Adjudicating Officer
CCP.20/2023
Order Pronounced In the result, it is ordered that the respondent should pay a compensation of Rs.5,00,000/- to the complainant for mental agony and hardship and also Rs.1,00,000/- as litigation expenses and these amounts should be paid within 90 days from the date of this order.
-
25 Feb 2025 Case diary, Adjudicating Officer
CCP.20/2023
Both sides present. Respondent side arguments heard. Written arguments also filed. Reply arguments by complainant side heard. Orders by 19.03.2025.
Next: 19 Mar 2025
-
25 Feb 2025 Cause list, Adjudicating Officer
CCP.20/2023 listed for hearing.
-
28 Jan 2025 Case diary, Adjudicating Officer
CCP.20/2023
Both sides present. At request by respondent side, respondent side arguments adjourned to 25.02.2025 NFA
Next: 25 Feb 2025
-
28 Jan 2025 Cause list, Adjudicating Officer
CCP.20/2023 listed for hearing.
-
8 Jan 2025 Case diary, Adjudicating Officer
CCP.20/2023
Both sides present. Complainant side files written submissions. Respondent side arguments by 28.01.2025.
Next: 28 Jan 2025
-
8 Jan 2025 Cause list, Adjudicating Officer
CCP.20/2023 listed for hearing.
-
11 Dec 2024 Case diary, Adjudicating Officer
CCP.20/2023
I.A.117/2024: No counter endorsed. Petition allowed. CCP.20/2023: Both sides present. I.A.117/2024 allowed. Arguments at request by complainant side, adjourned to 08.01.2025.
Next: 8 Jan 2025
-
11 Dec 2024 Cause list, Adjudicating Officer
CCP.20/2023 listed for hearing.
-
27 Nov 2024 Case diary, Adjudicating Officer
CCP.20/2023
I.A.117/2024: Petition appears in person today. Petition is the power agent of original complainant signature verified. Accepted. For counter & disposal adjourned to 11.12.2024.
Next: 11 Dec 2024
-
27 Nov 2024 Cause list, Adjudicating Officer
CCP.20/2023 listed for hearing.
-
25 Sep 2024 Case diary, Adjudicating Officer
CCP.20/2023
Complainant side not present. Twice the is called complainant side not turned up. Complainant remains absent for the past three hearings and for conditional orders today. Hence, CCP is dismissed for default without costs.
From the cause lists and case diaries TN RERA publishes, matched to this order by its complaint number.
Project details
Project "VGN Temple Town" at Thiruverkadu Village, Poonamallee Taluk, Tiruvallur District.
Order document
Loading PDF viewer...
Related cases
- CCP No.119/2020 Shri Aishwar Muthuraman v. 1) Green Avenue Homes & Gardens and 2) Bennett Property Hold... SMB 09 Oct 2026
- I.A.No.16/2025 in C.No.148/2024 1) Avigna Private Limited and 2) Avigna Irra Private Limited v. 1) Evernest Commercial Property Private Limited, 2) Evernest... Authority 05 Oct 2026
- 16/2024 1) Dr. Thirupathi Raja and 2) Dr. S.Geetha v. Bennett Property Holdings Company Ltd., and 3 Others Adjudicating 02 Sep 2026
- E.P.No.5/2025 in C.No.77/2023 Venkatakrishnan Ramaswamy v. Green Avenue Homes & Gardens Authority 16 Oct 2026
Need Complete Property Verification?
Get ownership details, EC records, FMB, zone checks, geo-insights & AI analysis - all in one place
Ask the records, or walk the map.
LandLens One answers from Tamil Nadu land law itself, cited to the page, then acts on the registers. One Map lights them up on the parcel. Your history stays in one place across both.
YOU APPROVE ANY SPEND
*Some tools are free of charge, but you need a credit balance to use LandLens One and One Map chat.