Complaint before the Adjudicating Officer
E.P.09/2024 CCP.56/2023
Parties, as the latest list prints them
- Complainant
- J.Yoganandan
- Respondent
- M/s.Annai Builders Real Estates Pvt Ltd
Hearings, newest first
-
12 Feb 2025 Case diary, item 1
As per endorsement, E.P. is dismissed as withdrawn. No costs.
-
12 Feb 2025 Cause list, item 1
Listed for hearing.
-
23 Jul 2024 Case diary, item 20
CCP.56/2023
Common order Pronounced: In the result, In CCP 77/2022 there is no order for any of the prayers in the complaint. In CCP 56/2023, the respondent should pay a compensation of Rs. 2,00,000/- to the complainant for the mental agony and also Rs. 50,000/-towards the costs and these amounts should be paid within 90 days from the date of this order. Sd/-***** Adjudicating Officer TNRERA, Chennai
-
3 Jul 2024 Case diary, item 30
CCP.56/2023
Both sides present. Respondent side arguments and reply by the complainant side also heard. For orders by 23.7.2024.
Next: 23 Jul 2024
-
3 Jul 2024 Cause list, item 30
-
5 Jun 2024 Case diary, item 18
CCP.56/2023 J.Yoganandan
Complainant and respondent side present.. P. A. of Rw1 filed. No documents for respondent. Respondent side evidence closed. Complainant side written arguments filed, for respondent side arguments by 03.7.2024.
Next: 3 Jul 2024
Read from the cause lists and case diaries TN RERA publishes. A listing is a dispute being heard, not a finding; the final order, once passed, is the decision.
Ask the records, or walk the map.
LandLens One answers from Tamil Nadu land law itself, cited to the page, then acts on the registers. One Map lights them up on the parcel. Your history stays in one place across both.
YOU APPROVE ANY SPEND
*Some tools are free of charge, but you need a credit balance to use LandLens One and One Map chat.