Complaint before the Single Member Bench

RCP.32/2025

Final order passed Listed 10 times

Parties, as the latest list prints them

Complainant
Zareena Begum
Respondent
M/s. Casagrand Civil Engineering Pvt Ltd., M/s. Ganesh & Ganesh

Hearings, newest first

  1. 7 Apr 2026 Case diary, item 16

    Both sides present. On previous hearing, complainant submits that he has received cheque dated 11.03.2026 from the respondent. Today, complainant submits that the cheque has been realized and filed memo of withdrawal stating that the matter is settled between the parties and the same is recorded. Counsel for the complainant also made endorsement to that effect. In view of the memo and endorsement, the RCP No. 32 of 2025 is dismissed as withdrawn.

  2. 7 Apr 2026 Cause list, item 16

    Listed for hearing.

  3. 24 Mar 2026 Case diary, item 23

    Both sides present. Complainant submits that today he has received cheque dated 11.03.2026 from the respondent is recorded. For realization of cheque, posted to 07.04.2026.

    Next: 7 Apr 2026, for realization of cheque

  4. 24 Mar 2026 Cause list, item 23
  5. 23 Dec 2025 Case diary, item 11

    Both sides present and submit that they have entered an MOU stating that the issue will be settled within 90 days from 23.12.2025 and the same is recorded. For reporting settlement or for filing proof affidavit by respondent, posted to 24.03.2026.

    Next: 24 Mar 2026, for reporting settlement or for filing proof affidavit by respondent

  6. 23 Dec 2025 Cause list, item 11
  7. 12 Dec 2025 Case diary, item 6

    Both sides present. Respondent submitted that the settlement talks are going on between the parties, hence seeks time to settle the issue. For reporting settlement or for filing proof affidavit by respondent, posted to 23.12.2025.

    Next: 23 Dec 2025, for reporting settlement or for filing proof affidavit by respondent

  8. 12 Dec 2025 Cause list, item 6
  9. 18 Nov 2025 Case diary, item 11

    Both sides present. Respondent again seeks time to file proof affidavit. Respondent is directed to file proof affidavit in the registry within 2 weeks from today, failing which a cost of Rs.3,000/- payable to CM Relief Fund. For proof affidavit by respondent, posted to 12.12.2025.

    Next: 12 Dec 2025, for proof affidavit by respondent

  10. 18 Nov 2025 Cause list, item 11
  11. 28 Oct 2025 Case diary, item 10

    Both sides present. Complainant's side documents are marked as Ex.A1 to Ex.A10 is recorded. For proof affidavit by respondent, posted to 18.11.2025.

    Next: 18 Nov 2025

  12. 28 Oct 2025 Cause list, item 10
  13. 26 Sep 2025 Case diary, item 6

    Both sides present. Proof affidavit filed by complainant is examined as CW-1 is recorded. For marking of complainant's side documents, posted to 28.10.2025.

    Next: 28 Oct 2025, for marking of complainant's side documents

  14. 26 Sep 2025 Cause list, item 6
  15. 22 Aug 2025 Case diary, item 12

    Both sides present. Counter filed by the respondent along with memo of cost is recorded. For proof affidavit by complainant, posted to 26.09.2025.

    Next: 26 Sep 2025

  16. 22 Aug 2025 Cause list, item 12
  17. 8 Jul 2025 Case diary, item 18

    Both sides present. M/s. Ganesh and Ganesh, Advocates filed vakalat for the respondent is recorded and seeks time to file counter. Respondent is directed to file counter in the registry within 2 weeks from today failing which a cost of Rs.2,500/- to be paid to the CM Relief Fund. For counter by respondent, posted to 22.08.2025.

    Next: 22 Aug 2025, for counter by respondent

  18. 8 Jul 2025 Cause list, item 18

    Listed for hearing.

  19. 29 Apr 2025 Case diary, item 4

    Both sides present. M/s. Ganesh and Ganesh, Advocates undertakes to file vakalat for the respondent is recorded. For filing vakalat and counter by respondent, posted to 08.07.2025.

    Next: 8 Jul 2025, for filing vakalat and counter by respondent

  20. 29 Apr 2025 Cause list, item 4

Read from the cause lists and case diaries TN RERA publishes. A listing is a dispute being heard, not a finding; the final order, once passed, is the decision.