4 Apr 2025 Case diary, item 38
Both sides present. Complainant filed calculation table is recorded. Heard both sides. Reserved for orders.
-
4 Apr 2025 Cause list, item 38
Listed for hearing.
-
14 Feb 2025 Case diary, item 18
Both sides present. Respondent filed copy of the interest calculation sheet and the same was served to the complainant. For arguments, posted to 04.04.2025.
Next: 4 Apr 2025, for arguments
-
14 Feb 2025 Cause list, item 18
Listed for hearing.
-
3 Jan 2025 Case diary, item 33
Both sides present. For further arguments, posted to 14.02.2025.
Next: 14 Feb 2025
-
3 Jan 2025 Cause list, item 33
Listed for hearing.
-
6 Dec 2024 Case diary, item 21
Both sides present. Proof of service of written argument to the respondent by the complainant is recorded. Complainant seeks time for arguments. Posted to 03.01.2025 for arguments.
Next: 3 Jan 2025, for arguments
-
6 Dec 2024 Cause list, item 21
Listed for hearing.
-
18 Oct 2024 Case diary, item 18
The counsel for complainant absent. The counsel for respondent present. Posted to 06.12.2024 for filing proof of service of written arguments to the respondent by the complainant and for arguments.
Next: 6 Dec 2024, for filing proof of service of written arguments to the respondent by the complainant and for arguments
-
18 Oct 2024 Cause list, item 18
Listed for hearing.
-
4 Oct 2024 Cause list, item 24
Listed for hearing (Reposted by notification).
Next: 18 Oct 2024, reposted, as the list's notice says
Notice on this listNotification dated 03.10.2024 The following cases posted on 04.10.2024 have been reposted to 18.10.2024 on administrative grounds:-
-
5 Sep 2024 Case diary, item 13
RCP.48, 108/2023:- Complainant counsel present. Respondent counsel present. Memo of calculation submitted by the complainant is recorded. Reserved for orders. RCP.86/2023:- Complainant counsel present. Respondent counsel present. At the request of the complainant posted to 04/10/2024 for arguments.
Next: 4 Oct 2024, for arguments
-
5 Sep 2024 Cause list, item 15
Listed for hearing.
-
30 Aug 2024 Cause list, item 31
Listed for hearing (Reposted by notification).
Notice on this listTHE TAMILNADU REAL ESTATE REGULATORY AUTHORITY (TNRERA) PRESENT: THIRU.SUNIL KUMAR, I.P.S., (Retd), MEMBER-I 30.08.2024
-
22 Aug 2024 Case diary, item 13
Complainant counsel present. Respondent counsel present. Both parties argued and were heard in full. Written argument filed by the respondent is recorded. Posted to 30/08/2024 for written arguments of the complainant finally.
Next: 30 Aug 2024, for written arguments of the complainant finally
-
22 Aug 2024 Cause list, item 13
Listed for hearing.
-
8 Aug 2024 Cause list, item 29
Listed for hearing (Reposted by notification).
Notice on this listTHE TAMILNADU REAL ESTATE REGULATORY AUTHORITY (TNRERA) PRESENT: THIRU.SUNIL KUMAR, I.P.S., (Retd), CHAIRPERSON i/c 08.08.2024
-
18 Jun 2024 Case diary, item 37
Complainant counsel present. Respondent counsel present. Written arguments submitted. At the request of the complainant counsel posted to 08.08.2024 finally. The respondent is direct to share the documents with the complainant on or before 01.08.2024 along with receipt for arguments on 08.08.2024.
Next: 8 Aug 2024
-
18 Jun 2024 Cause list, item 37
Listed for hearing.
-
12 Apr 2024 Case diary, item 23
Complainant counsel present. Respondent counsel present. Both parties argued and were heard. Respondent submits his calculation sheet which is recorded and copy handed to the complainant. Posted to 18/06/2024 for arguments.
Next: 18 Jun 2024, for arguments
-
12 Apr 2024 Cause list, item 23
Listed for hearing.
-
28 Mar 2024 Cause list, item 27
Listed for hearing.
-
22 Feb 2024 Cause list, item 20
RCP. 86/2023 22.02.2024 are reposted to 28.03.2024.
Listed for hearing (Reposted by notification).
Notice on this listTHE TAMILNADU REAL ESTATE REGULATORY AUTHORITY (TNRERA) PRESENT: THIRU.SUNIL KUMAR, I.P.S., (Retd) 22.02.2024
-
12 Jan 2024 Cause list, item 17
Listed for hearing at 12 Noon.
-
9 Jan 2024 Cause list, item 16
Listed for hearing (Reposted by notification).
Notice on this listTHE TAMILNADU REAL ESTATE REGULATORY AUTHORITY (TNRERA) PRESENT: THIRU.SUNIL KUMAR, I.P.S., (Retd) 09.01.2024
-
16 Nov 2023 Cause list, item 10
Listed for hearing.
-
31 Oct 2023 Cause list, item 24
Listed for hearing.
-
7 Sep 2023 Cause list, item 11
Listed for hearing.
-
2 Aug 2023 Cause list, item 17
Listed for hearing.
-
25 Jul 2023 Cause list, item 16
Listed for hearing (Reposted by notification).
Notice on this listBEFORE THE TAMILNADU REAL ESTATE REGULATORY AUTHORITY (TNRERA) PRESENT: THIRU.SUNIL KUMAR, I.P.S., (Retd) 25.07.2023
Read from the cause lists and case diaries TN RERA publishes. A listing is a dispute being heard, not a finding; the final order, once passed, is the decision.
Ask the records, or walk the map.
LandLens One answers from Tamil Nadu land law itself, cited to the page, then acts on the registers. One Map lights them up on the parcel. Your history stays in one place across both.
YOU APPROVE ANY SPEND
*Some tools are free of charge, but you need a credit balance to use LandLens One and One Map chat.