Complaint before the TN RERA Authority
C.No.028/2025
Parties, as the latest list prints them
- Complainant
- 1.R.Kasthuri 2.R.Gowtham Chandar
- Respondent
- M/s.Jones Foundations Pvt.Ltd.
Hearings, newest first
-
16 Mar 2026 Case diary, item 9
The Complainants called absent. The counsel for the Respondent present and submitted that as per the directions of this Authority during last hearing the issues have been settled and to that effect the copy of the Memorandum of Compromise duly signed by the Complainants and the Respondents is filed. As per the MoU, the issues between both the parties have been settled amicably as per the terms of the MoU. Therefore, the above complaint is closed as settled.
-
16 Mar 2026 Cause list, item 9
-
4 Feb 2026 Case diary, item 21
The Complainants called absent. The Counsel for the Respondent present and already filed a Memo in the Registry enclosing the copy of the orders of the Hon’ble High Court in CS No.216 of 2025 dated 06.11.2025 wherein it is stated that the parties have entered into MoU dated 31.10.2025 containing the detailed terms of settlement and the terms of MoU may be read as part and parcel of the Memorandum of Compromise. The Respondent is directed to file a copy of the aforesaid MoU entered between the parties which has been referred by the Hon’ble High Court in its order dated 06.11.2025. Posted to 16.03.2026 for filing copy of the MoU by the Respondent.
Next: 16 Mar 2026, for filing copy of the MoU by the Respondent
-
4 Feb 2026 Cause list, item 21
-
15 Dec 2025 Case diary, item 7
Both the Complainants and the Respondent called absent. The Counsel for the Respondent appeared before the Authority at the end of Day’s proceedings and submitted that in CMSA No.216 of 2025 orders have been passed by the Hon’ble High Court of Madras. The Authority directs the Respondent to file copy of the above said orders of the Hon’ble High Court within one week before the Registry with copy served to the Complainants by RPAD. The matter is posted to 04.02.2026 for reporting settlement.
Next: 4 Feb 2026, for reporting settlement
-
15 Dec 2025 Cause list, item 7
-
3 Nov 2025 Case diary, item 4
Both parties called absent. The matter is adjourned to 15.12.2025 for reporting settlement or for filing Counter by the Respondent.
Next: 15 Dec 2025, for reporting settlement or for filing Counter by the Respondent
-
3 Nov 2025 Cause list, item 4
-
22 Sep 2025 Case diary, item 11
The Complainants called absent. The Counsel for Respondent present and submitted that settlement talks are going on between the parties and sought time to report settlement or for filing Counter. Posted to 03.11.2025 for reporting settlement or for filing Counter by the Respondent.
Next: 3 Nov 2025, for reporting settlement or for filing Counter by the Respondent
-
22 Sep 2025 Cause list, item 11
-
10 Sep 2025 Case diary, item 2
The Complainants called absent The Counsel for Respondent present and again sought time to file Counter. The Authority directs the Respondent to file Counter within two weeks in the Registry failing which cost of Rs.2,500/- will be imposed to be paid to the CM Relief Fund. Posted to 22.09.2025.
Next: 22 Sep 2025
-
10 Sep 2025 Cause list, item 2
-
16 Jul 2025 Case diary, item 1
028/2025
The Counsel for Complainant present The Counsel M/s. Harishankar for Respondent present and filed vakalat and sought time to file Counter. Posted to 10.09.2025 for filing Counter by the Respondent.
Next: 10 Sep 2025, for filing Counter by the Respondent
-
16 Jul 2025 Cause list, item 1
Read from the cause lists and case diaries TN RERA publishes. A listing is a dispute being heard, not a finding; the final order, once passed, is the decision.
Ask the records, or walk the map.
LandLens One answers from Tamil Nadu land law itself, cited to the page, then acts on the registers. One Map lights them up on the parcel. Your history stays in one place across both.
YOU APPROVE ANY SPEND
*Some tools are free of charge, but you need a credit balance to use LandLens One and One Map chat.