Complaint before the TN RERA Authority
C.No.029/2025
Parties, as the latest list prints them
- Complainant
- M/s.Kavimani A1,B1, C1, D1 & W, X, Y, Z Block site Owners Association
- Respondent
- M/s.Prince Houcing Chennai Private Limited.
Hearings, newest first
-
24 Sep 2025 Case diary, item 26
The Counsel for the Complainant present. The Counsel for Respondent present and filed Counter and served the copy to the Counsel for the Complainant. Both the Counsels made their oral submissions. The Authority heard both the parties and they are at liberty to file their written submission of arguments, if any, before the Registry by serving copy with each other. Reserved for orders.
-
24 Sep 2025 Cause list, item 26
-
10 Sep 2025 Case diary, item 3
The Counsel for the Complainant present. The Counsel M/s. Vijaya Bharathi for Respondent present and filed vakalat and sought time to file Counter. The Authority directs the Respondent to file Counter within two weeks in the Registry failing which cost Rs.2,500/- will be imposed to be paid to CM Relief fund. It is brought to the notice of the Authority that this project is not a registered project, but in the year 2019 there is already a direction in C.Nos.80 to 115 of 2019 vide this Authority’s order dated 17.10.2019 for registration of this real estate project with TNRERA. Posted to 24.09.2025.
Next: 24 Sep 2025, for registration of this real estate project with TNRERA
-
10 Sep 2025 Cause list, item 3
-
16 Jul 2025 Case diary, item 2
029/2025
The Counsel for the Complainant present. The Counsel M/s. Jyoshna for Respondent present and sought time to file vakalat and Counter. The Complainant Counsel sought permission under Section 8 of the Act to carry out the remaining construction of the apartments. There is a preliminary issue of maintainability of this Complaint, since this project is not a registered project. Hence, the Authority directs both the parties to demonstrate whether this project is registered or not before next hearing. Posted to 10.09.2025 for filing vakalat and Counter by the Respondent.
Next: 10 Sep 2025, for filing vakalat and Counter by the Respondent
-
16 Jul 2025 Cause list, item 2
Read from the cause lists and case diaries TN RERA publishes. A listing is a dispute being heard, not a finding; the final order, once passed, is the decision.
Ask the records, or walk the map.
LandLens One answers from Tamil Nadu land law itself, cited to the page, then acts on the registers. One Map lights them up on the parcel. Your history stays in one place across both.
YOU APPROVE ANY SPEND
*Some tools are free of charge, but you need a credit balance to use LandLens One and One Map chat.