Complaint before the TN RERA Authority

C.293/2021

Final order passed Listed 6 times

Parties, as the latest list prints them

Complainant
1. M/s. Pine Flat Owners Welfare Association (PFOWA) 1. M/s. Maple Flat Owners Welfare Association (MFOWA)
Respondent
1. M/s. Alliance Projects 2. M/s. Alliance Infrastructure Projects (P) Ltd., 3. B.V.Subba Reddy (Died) 4. Manoj Sai Namburu

Hearings, newest first

  1. 23 Sep 2026 Case diary, item 4

    Counsel for Complainant in C.No.293/2021 present. Complainant party in person in C.No.294/2021 present Respondents called absent. The Complainants during the arguments submitted that the lifts are not working due to poor maintenance, swimming pool; storm water drain, adequate water supply are not provided. Also the Complainants submitted that in spite of the direction by this Authority to register this real estate project, the Respondents have not complied and the penalty imposed for non compliance of the orders of this Authority also not paid. As the Respondents are called absent, the opportunity to argue the matter by the Respondents are closed. Reserved for orders.

  2. 23 Sep 2026 Cause list, item 4
  3. 10 Aug 2026 Case diary, item 6

    Complainants and the Respondents called absent. Adjourned to 23.09.2026 for further adjudication.

    Next: 23 Sep 2026, for further adjudication

  4. 10 Aug 2026 Cause list, item 6

    Listed for hearing at 3.00 P.M..

  5. 13 Jul 2026 Case diary, item 9

    The Complainants called absent. The Counsel for the Respondents-1, 2 & 4 present and sought time to register this real estate project with TNRERA. The Authority while passing orders on maintainability of these Complaints on 11.05.2026 had directed the Respondent promoter to register the project with TNRERA on or before 30.06.2026 as this project is squarely falls within the ambit of Section-3 of the RERA Act. However, so far, it has not been done by the Respondent promoter. The learned counsel for the Respondents submitted that due to oversight, he missed this order and could not be conveyed to the Respondents and sought two weeks time. The Authority considering the submissions of the Respondent promoter grants two weeks time to register this real estate project with TNRERA, failing which a penalty of Rs.10,000/- for each day delay will be imposed if the project is not registered within two weeks i.e. by 27.07.2026. The Registry is directed to inform the above to the Registration wing of this Authority so that the said penalty is collected before the registration is granted for the aforesaid project. Posted to 10.08.2026 for further adjudication.

    Next: 10 Aug 2026, for further adjudication

  6. 13 Jul 2026 Cause list, item 9
  7. 24 Nov 2025 Case diary, item 17

    The Complainant party in person present in C.No.293/2021. The counsel for the Complainant present in C.No.294/2021. The representing counsel for Respondent present The counsel for the Complainant argued the matter in respect of maintainability of the Complaint. The representing counsel for the Respondent present and sought one more chance to argue the matter. Enough opportunity has been given to the Respondent to argue the matter, but the Respondent is not ready to argue the matter. However, the Respondents are at liberty to file written submission of arguments in IA within one week in the Registry, if not filed already by serving copy to the Complainants by RPAD. Reserved for orders in IA.

  8. 24 Nov 2025 Cause list, item 17

    Listed for hearing at 3.00 P.M. (Arguments).

  9. 5 Nov 2025 Case diary, item 13

    The Complainant party in person present in C.No.293/2021 and filed written arguments with copy served to the Respondents-1, 2 & 4. The Counsel for the Complainant present in C.No294/2021 and filed written arguments with copy served to the Respondents- 1, 2 & 4. The Counsel for Respondents-1, 2 & 4 present. The matter is posted to 24.11.2025 for arguments by both the parties on the preliminary issue of registration of this real estate project.

    Next: 24 Nov 2025, for arguments by both the parties on the preliminary issue of registration of this real estate project

  10. 5 Nov 2025 Cause list, item 13

    Listed for hearing at 3.00 P.M. (Arguments).

  11. 13 Oct 2025 Case diary, item 31

    The Counsel for the Complainants present The Counsel for Respondent present This Complaint is relating to unregistered project. However, the Complainants included in their prayer to direct the Respondent to register this real estate project. The counsel for the Respondent argued the matter and wants to file an IA with prayer to reject this complaint as it is not a i d j registered project. The Authority declined to accept the IA and decided first to take up the preliminary issue of whether this project is to be registered or not. The matter is posted to 05.11.2025 for arguments by both the parties on the preliminary issue of registration of this real estate project.

    Next: 5 Nov 2025, for arguments by both the parties on the preliminary issue of registration of this real estate project

  12. 13 Oct 2025 Cause list, item 31

    Listed for hearing (Arguments).

The same complaint number was also listed before Single Member Bench.

Read from the cause lists and case diaries TN RERA publishes. A listing is a dispute being heard, not a finding; the final order, once passed, is the decision.