Complaint before the TN RERA Authority

C.No.77/2025

No final order yet Listed 4 times

Parties, as the latest list prints them

Complainant
1)Tmt. R. Krishnapriya 2)Thiru V. Manimuthukumar
Respondent
M/s. VNR Homes Pvt. Ltd. Rep. by Tmt. R. Madhumathy & Thiru V.N. Raghupathy Door No.5/20, Blue Beach Road Neelangarai Chennai-600 115.

Hearings, newest first

  1. 1 Apr 2026 Case diary, item 8

    The Complainants party in person present and filed Memo for recording the compliance by the Respondent and for closure of the Complaint. The learned counsel for Respondent present and filed additional documents and submitted that the rectification work has been done as per the directions of this Authority. The Complainants party in person have also concurred and placed their thanks to the Authority for resolving the issue. Since the rectification work has been carried out by the Respondent, the Authority recording the Memo filed by the Complainants, closes the Complaint No.77/2025 as settled.

  2. 1 Apr 2026 Cause list, item 8

    Listed for hearing.

  3. 4 Mar 2026 Case diary, item 14

    77/2025

    The Complainants party in person present. The counsel for Respondent present and filed Counter along with typed set documents and served copy to the complainants. The Complainants submitted that the seepage issue in the car parking area is yet to be rectified. The learned counsel for the Respondent submitted that within three weeks the seepage issue in the car parking area will be rectified. The Authority directs the Respondent to expedite the work and report compliance during next hearing. The Authority also directs the Complainants to go-operate with the Respondent in rectifying the seepage issue. Posted to 01.04.2026 for reporting compliance by Respondent.

    Next: 1 Apr 2026, for reporting compliance by Respondent

  4. 4 Mar 2026 Cause list, item 14

    77/2025

    Listed for hearing at 3.00 P.M..

  5. 16 Feb 2026 Case diary, item 2

    77/2025

    The Complainants party in person present. The New Counsel M/s. G.Vivekanand for the Respondent present and undertook to file vakalat and Counter. The Complainant party in person submitted that there is seepage in the car parking area of the Complainant and sought an interim direction to the Respondent to rectify the issue immediately. The Counsel for the Respondent submitted that they are taking steps to resolve the issue and sought two weeks time to address the issue and report compliance. Accordingly, the Authority directs the Respondent to rectify the seepage issue in the car parking area of the Complainants within 15 days from today and report compliance during next hearing. Posted to 04.03.2026 for filing vakalat along with Counter and for reporting compliance.

    Next: 4 Mar 2026, for filing vakalat along with Counter and for reporting compliance

  6. 16 Feb 2026 Cause list, item 2

    77/2025

    Listed for hearing at 3.00 P.M..

  7. 5 Jan 2026 Case diary, item 1

    77/2025

    The Complainants party in person present. The Counsel M/s.Krishna Sidhar for Respondent present and undertake to file vakalat and Counter. Posted to 16.02.2026 for filing vakalat and Counter by Respondent.

    Next: 16 Feb 2026, for filing vakalat and Counter by Respondent

  8. 5 Jan 2026 Cause list, item 1

    C.No.77/2025 (NEW)

    Listed for hearing at 3.00 P.M. (New).

Read from the cause lists and case diaries TN RERA publishes. A listing is a dispute being heard, not a finding; the final order, once passed, is the decision.