Single Member Bench order, refund case
RCP No.26/2023
Parties involved
- Complainant
- 1) C.S. Iysewarya Bharathi and 2) S. Ganesh
- Respondent
- Alliance Business Parks Pvt. Ltd.,
Hearings of this complaint (listed on 23 days)
-
28 Oct 2025 Case diary, Single Member Bench
RCP.26/2023
Counsel for complainants present. Respondent absent. Complainants submitted that the respondent has directly paid the entire amount to the Bank, hence seeks withdrawal of the complaint and complainants also made endorsement to that effect. In view of the endorsement and submissions made by the complainants, the RCP No. 26 of 2023 is closed as withdrawn.
-
28 Oct 2025 Cause list, Single Member Bench
RCP.26/2023 listed for hearing.
-
19 Sep 2025 Case diary, Single Member Bench
RCP.26/2023
Counsel for complainants present. Respondent absent. On previous hearing, respondent is directed to file additional documents in the registry if any by serving copy to other side. Today, respondent called absent. Hence, chance for filing additional documents by the respondent is closed. For arguments, posted to 28.10.2025.
Next: 28 Oct 2025, for arguments
-
19 Sep 2025 Cause list, Single Member Bench
RCP.26/2023 listed for hearing.
-
2 Sep 2025 Case diary, Single Member Bench
RCP.26/2023
Counsel for complainants present. Respondent absent. Respondent is directed to file additional documents in the registry if any by serving copy to other side. For filing additional documents by the respondent, posted to 19.09.2025.
Next: 19 Sep 2025, for filing additional documents by the respondent
-
2 Sep 2025 Cause list, Single Member Bench
RCP.26/2023 listed for hearing.
-
19 Aug 2025 Case diary, Single Member Bench
RCP.26/2023
Both sides present. Complainants side additional documents are marked Ex.A9 to Ex.A15 is recorded. Respondent seeks time to file additional documents. For filing additional documents by the respondent, posted to 02.09.2025.
Next: 2 Sep 2025, for filing additional documents by the respondent
-
19 Aug 2025 Cause list, Single Member Bench
RCP.26/2023 listed for hearing.
-
1 Jul 2025 Case diary, Single Member Bench
RCP.26/2023
Both sides present. Complainants filed additional proof affidavit is recorded. For marking of complainants side additional documents, posted to 19.08.2025.
Next: 19 Aug 2025, for marking of complainants side additional documents
-
1 Jul 2025 Cause list, Single Member Bench
RCP.26/2023 listed for hearing.
-
29 Apr 2025 Case diary, Single Member Bench
RCP.26/2023
Both sides present. Respondent made no objection to the IA No. 36/2025 to receive additional documents. Hence, IA No. 36/2025 is allowed. For filing proof affidavit by complainants, posted to 01.07.2025.
Next: 1 Jul 2025, for filing proof affidavit by complainants
-
29 Apr 2025 Cause list, Single Member Bench
RCP.26/2023 listed for hearing.
From the cause lists and case diaries TN RERA publishes, matched to this order by its complaint number.
Project details
Project "Alliance Galleria Residences" at 200 Feet MMRD Road, Zamin Pallavaram Village, Chennai.
Order document
Loading PDF viewer...
Related cases
- E.P. No.22/2026 in RCP No.227/2022 N. Josiah Soloman v. 1) Alliance Business Park Pvt. Ltd., and 2) Alliance Project... SMB 06 Nov 2026
- RCP No.58/2026 Ruchi Dayal v. Alliance Budget Housing India Pvt. Ltd., SMB 13 Oct 2026
- RCP No.47/2025 R. Vasanthakumar v. Alliance Business Parks Private Limited SMB 13 Oct 2026
- E.P.No.5/2025 in C.No.77/2023 Venkatakrishnan Ramaswamy v. Green Avenue Homes & Gardens Authority 16 Oct 2026
Need Complete Property Verification?
Get ownership details, EC records, FMB, zone checks, geo-insights & AI analysis - all in one place
Ask the records, or walk the map.
LandLens One answers from Tamil Nadu land law itself, cited to the page, then acts on the registers. One Map lights them up on the parcel. Your history stays in one place across both.
YOU APPROVE ANY SPEND
*Some tools are free of charge, but you need a credit balance to use LandLens One and One Map chat.