Single Member Bench order, refund case
CCP No.45/2022, 46/2022, 119/2022 to 124/2022 and 166/2022
Parties involved
- Complainant
- G. Edwin and Others
- Respondent
- Ozone Projects Pvt. Ltd.,
Hearings of this complaint (listed on 10 days)
-
6 Jun 2025 Case diary, Single Member Bench
CCP.45/2022
Both sides present. Written arguments filed by the complainants is recorded. Complainants filed list of orders passed by this Authority is recorded. Common written arguments filed by the respondent is also recorded. Complainants seek time to file reply to the written arguments filed by the respondent. Complainants are directed to file the reply to the written arguments in the registry within one week from today by serving copy to the respondent. Heard both sides. Reserved for orders.
-
6 Jun 2025 Cause list, Single Member Bench
CCP.45/2022 listed for hearing.
-
18 Mar 2025 Case diary, Single Member Bench
CCP.45/2022
Both sides present. Complainants seek time for arguments. For arguments, posted to 06.06.2025.
Next: 6 Jun 2025
-
18 Mar 2025 Cause list, Single Member Bench
CCP.45/2022 listed for hearing.
-
4 Feb 2025 Case diary, Single Member Bench
CCP.45/2022
Both sides present. In all the CCP's, respondent filed memo of cost is recorded. In CCP Nos. 45, 46, 120, 121, 122, 123, 124 and 166 of 2022, proof affidavit filed by the respondent with no documents is examined as RW-1 is recorded. For arguments, posted to 18.03.2025.
Next: 18 Mar 2025, for arguments
-
4 Feb 2025 Cause list, Single Member Bench
CCP.45/2022 listed for hearing.
-
20 Dec 2024 Case diary, Single Member Bench
CCP.45/2022
Counsel for complainants present. Counsel for respondent absent. The Authority has imposed a cost of Rs.5,000/- totally to be paid by the respondent to the CM Relief Fund. For filing proof affidavits of the respondent and proof of cost paid to CM relief fund, posted to 04.02.2025 finally.
Next: 4 Feb 2025
-
20 Dec 2024 Cause list, Single Member Bench
CCP.45/2022 listed for hearing.
-
15 Nov 2024 Case diary, Single Member Bench
CCP.45/2022
Both sides present. For filing proof affidavit of respondent, posted to 20.12.2024 finally.
Next: 20 Dec 2024
-
15 Nov 2024 Cause list, Single Member Bench
CCP.45/2022 listed for hearing.
-
15 Oct 2024 Case diary, Single Member Bench
CCP.45/2022
The counsel for complainants called absent. The counsel for respondent called absent. Posted to 15.11.2024 for proof affidavit of the respondent finally.
Next: 15 Nov 2024, for proof affidavit of the respondent finally
-
15 Oct 2024 Cause list, Single Member Bench
CCP.45/2022 listed for hearing.
From the cause lists and case diaries TN RERA publishes, matched to this order by its complaint number.
Project details
Project "The Metrozone" at Pillaiyar Koil Street (Jawaharlal Nehru Road), Anna Nagar, Chennai - 600040.
Order document
Loading PDF viewer...
Related cases
- CCP No.123/2021 A. Naveen Victor v. 1) Ozone Projects Pvt. Ltd., and 2) The Metrozone Apartments... SMB 27 Oct 2026
- E.A. No.6/2025 in E.P. No.79/2021 in CCP No.15/2020 Sushil Agarwal v. Ozone Projects Pvt. Ltd., SMB 30 Jun 2026
- E.A. No.5/2025 in E.P. No.78/2021 in CCP No.16/2020 1) Anjana Gupta and 2) Anil Kumar Gupta v. Ozone Projects Pvt. Ltd., SMB 30 Jun 2026
- E.P. No.22/2026 in RCP No.227/2022 N. Josiah Soloman v. 1) Alliance Business Park Pvt. Ltd., and 2) Alliance Project... SMB 06 Nov 2026
Need Complete Property Verification?
Get ownership details, EC records, FMB, zone checks, geo-insights & AI analysis - all in one place
Ask the records, or walk the map.
LandLens One answers from Tamil Nadu land law itself, cited to the page, then acts on the registers. One Map lights them up on the parcel. Your history stays in one place across both.
YOU APPROVE ANY SPEND
*Some tools are free of charge, but you need a credit balance to use LandLens One and One Map chat.