TNRERA Authority order (Form M)
417/2019
Parties involved
- Complainant
- Serene Rose Residents Welfare Association
- Respondent
- Serene Senior Living (P) Ltd., and Columbia Pacific Communities Pvt. Ltd.,
Hearings of this complaint (listed on 10 days)
-
12 Oct 2026 Case diary, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019
Counsel for the Execution Petitioner present and submitted that the interim stay granted in CMSA No.19/2022 by the Hon’ble High Court still continues. Respondents called absent. Posted to 14.12.2026 to ascertain the status of Stay.
Next: 14 Dec 2026, for ascertain the status of Stay
-
12 Oct 2026 Cause list, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019 listed for hearing at 3.00 P.M..
-
12 Aug 2026 Case diary, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019
Counsel for the Execution Petitioner present and submitted that the interim stay granted in CMSA No.19/2022 by the Hon’ble High Court still continues. Respondents called absent. Posted to 12.10.2026 for status of Stay.
Next: 12 Oct 2026, for status of Stay
-
12 Aug 2026 Cause list, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019 listed for hearing at 3.00 P.M..
-
29 Jul 2026 Case diary, TN RERA Authority
E.P.No.12/2026 in C.No.417/2019
Counsel for Execution Petitioner present Counsel for Respondent-1 present. Respondent-2 called absent. The prayer is against the Respondent-2 the service provider of this project i.e. to handover the maintenance of common areas and common amenities to the Complainant/Execution Petitioner Association by Respondent-2. The Authority heard both the Execution Petitioner and the Respondent- 1. Reserved for orders.
-
1 Jul 2026 Case diary, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019
The counsel for the Execution Petitioner present and filed a memo stating that the interim stay granted by the Hon’lbe High Court of Madras in CMSA No.19/2022 is still continues. The counsel for the Execution Petitioner has also submitted that the copy of the memo has already been served to the Respondent. The Respondents called absent. In view of the interim stay by the Hon’ble High Court of Madras, the matter is adjourned to 12.08.2026 for reporting the status of the Stay.
Next: 12 Aug 2026, for reporting the status of the Stay
-
1 Jul 2026 Cause list, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019 listed for hearing at 3.00 P.M..
-
6 Apr 2026 Case diary, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019
The counsel for the Execution Petitioner present Neither the counsel for the Respondents-1 and 2 nor the Respondents-1 & 2 appeared. At the request of the counsel for the Execution Petitioner, the case is adjourned to 01.07.2026 for further proceedings.
Next: 1 Jul 2026, for further proceedings
-
6 Apr 2026 Cause list, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019 listed for hearing at 3.00 P.M..
-
8 Dec 2025 Case diary, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019
The counsel for the Execution Petitioner present. The counsel for the Respondent-1 present. The Respondent-2 called absent. The Counsel for Respondent-1 submitted that the interim stay is still continued. The Counsel for the Execution Petitioner submitted that they have moved a petition before the Hon’ble High Court for an early hearing of the CMSA No.19/2022 and the Hon’ble High Court has decided to hear the matter during 2nd week of March, 2026. Posted to 06.04.2026.
Next: 6 Apr 2026
-
8 Dec 2025 Cause list, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019 listed for hearing at 3.00 P.M..
-
24 Sep 2025 Case diary, TN RERA Authority
E.P.No.18/2021 in C.No.417/2019
The Counsel for the Execution Petitioner present. The Counsel for the Respondent-1 present. The Counsel for the Respondent-2 present. The Counsels for the Respondents submitted that stay granted by the Hon’ble High Court of Madras in CMSA No.19/2022 continues and sought adjournment of this Execution Petition till the CMSA No.19/2022 is concluded. The case is adjourned to 08.12.2025 for further proceedings.
Next: 8 Dec 2025, for further proceedings
From the cause lists and case diaries TN RERA publishes, matched to this order by its complaint number.
Project details
Project "Serene Indus Valley" at T.S.No.378/2A part, 2B, 38/2A1 part, 2B, 3B, 3A2, 385/4A2B part, 385/3 part and 385/4A1 of Perur Chetty Pallayam Village, Coimbatore.
Order document
Loading PDF viewer...
Related cases
- E.P.No.12/2026 in C.No.417/2019 Serene Rose Residents Welfare Association v. 1) Serene Senior Living Pvt. Ltd., and 2) Columbia Pacific C... Authority 04 Aug 2026
- CCP No.130/2021, 186/2021, 194/2021, 195/2021, 196/2021, 200/2021, 285/2021 and 332/2021 P.V. Muralee Kesavan and Others v. 1) Serene Senior Living Pvt. Ltd., and 2) Columbia Pacific C... SMB 05 Apr 2024
- E.P. No.39/2022 in CCP No.284/2021 1) Geeta Shekhar and 2) Shekhar Murthy v. 1) Serene Senior Living Pvt. Ltd., and 2) Adinath Srinivasa... Adjudicating 12 Dec 2022
- E.A.No.2/2026 in E.P.No.27/2024 in C.No.212/2019 Catalyst Trusteeship Limited v. 1) Sare Squires Association and 2) Sare Shelters Projects Pv... Authority 29 Sep 2026
Need Complete Property Verification?
Get ownership details, EC records, FMB, zone checks, geo-insights & AI analysis - all in one place
Ask the records, or walk the map.
LandLens One answers from Tamil Nadu land law itself, cited to the page, then acts on the registers. One Map lights them up on the parcel. Your history stays in one place across both.
YOU APPROVE ANY SPEND
*Some tools are free of charge, but you need a credit balance to use LandLens One and One Map chat.