TNRERA Authority order (Form M)

I.A.No.10/2025 in C.No.150/2022

Order dated 21 Apr 2025 Complaint year 2022

Parties involved

Complainant
SB Aditya Housing Infra Pvt. Ltd., and Others
Respondent
R. Athmanathan and Others

Hearings of this complaint (listed on 21 days)

  1. 16 Nov 2026 Case diary, TN RERA Authority

    C.No.150/2022

    Counsel for Complainants-1 to 12 present Counsel for the 13th Complainant present All the Respondents called absent. Posted to 07.12.2026.

    Next: 7 Dec 2026

  2. 16 Nov 2026 Cause list, TN RERA Authority

    C.No.150/2022 listed for hearing at 3.00 P.M.

  3. 5 Oct 2026 Case diary, TN RERA Authority

    C.No.150/2022

    Complainants-1 to 12 called absent Counsel for the 13th Complainant present Counsel for Respondents 1 to 4 present Counsel for Respondents-5 & 6 present and filed vakalat along with IA for impleading the proposed Respondents-7 & 8 in this proceeding. The Authority directs the Respondents-5 & 6 to issue notice to the proposed 7th & 8th Respondents. The Authority directs all other parties to file Counter in IA on or before next hearing. Posted to 16.11.2026.

    Next: 16 Nov 2026

  4. 5 Oct 2026 Cause list, TN RERA Authority

    C.No.150/2022 listed for hearing at 3.00 P.M..

  5. 17 Aug 2026 Case diary, TN RERA Authority

    C.No.150/2022

    Counsel for the Complainants-1 to 12 present Counsel for the 13th Complainant present Counsel for Respondents 1 to 4 present Counsel for 5th and 6th Respondent present and sought time to file Counter. The 5th & 6th Respondents are directed to file counter within two weeks before the Registry. Posted to 05.10.2026.

    Next: 5 Oct 2026

  6. 17 Aug 2026 Cause list, TN RERA Authority

    C.No.150/2022 listed for hearing at 3.00 P.M..

  7. 13 Jul 2026 Case diary, TN RERA Authority

    150/2022

    The counsel for the Complainants-1 to 12 present The counsel for the 13th Complainant present The Respondents 1 to 4 called absent The counsel for the 5th Respondent and the proposed 6th Respondent present. The learned counsel for the 5th Respondent and the proposed 6th Respondent filed copy of the sale and construction agreement entered between the proposed 6th Respondent and 1st Respondent. The limited prayer in the IA No.4/2026 filed by the 5th Respondent and the proposed 6th Respondent is to implead M/s.Thirupathy Investors as 6th Respondent in this proceeding. The Complainants 1 to 12 and...

    Next: 17 Aug 2026, for filing counter by th Respondent

  8. 13 Jul 2026 Cause list, TN RERA Authority

    C.No.150/2022 (Arguments) listed for hearing (Arguments).

  9. 8 Jun 2026 Case diary, TN RERA Authority

    150/2022

    The counsel for the Complainants-1 to 12 present and endorsed their no objection in the IA No.4/2026 filed by the 5th Respondent to implead M/s. Thirupathy Investors as 6th Respondent in this proceeding. The counsel for the 13th impleaded Complainant present and already filed their no objection to implead M/s. Thirupathy Investors as 6th Respondent in this proceeding. The Respondents 1 to 4 called absent The 5th impleaded Respondent Mr. Ramji Jaganathan present and undertook to file documents in support of the IA No.4/2026 filed by them to implead M/s.Thirupathy Investors as proposed 6th Respo...

    Next: 13 Jul 2026, for arguments in the IA No

  10. 8 Jun 2026 Cause list, TN RERA Authority

    C.No.150/2022 (Arguments) listed for hearing at 3.00 P.M. (Arguments).

  11. 8 Apr 2026 Case diary, TN RERA Authority

    C.150/2022

    The counsel for the Complainants-1 to 12 present and sought time to argue the matter by their senior counsel. The representing counsel for the 13th impleaded Complainant present The Respondents 1 to 4 called absent The 5th impleaded Respondent Mr. Ramji Jaganathan present. The proposed 6th Respondent M/s.Thirupathy Investors present. Posted to 08.06.2026 for arguments in the IA No.4/2026. The counsel the Complainants present and filed IA to implead Respondents 17 to 22 and sought permission to take private notice. The Respondents 1 to 4 called absent The counsel for the Respondents-5 to 16 pre...

    Next: 8 Jun 2026, for arguments

  12. 8 Apr 2026 Cause list, TN RERA Authority

    C.150/2022 listed for hearing at 3.00 P.M. (Arguments).

See all 40 entries

From the cause lists and case diaries TN RERA publishes, matched to this order by its complaint number.

Project details

Project "Lotus Enclave" at Virugambakkam Village, Mambalam Taluk, Chennai District.

Order document

Loading PDF viewer...

Need Complete Property Verification?

Get ownership details, EC records, FMB, zone checks, geo-insights & AI analysis - all in one place

Ownership Details
EC Records
FMB Sketch
Zone Checks
Geo-Insights
AI Analysis
Try VerifyMyLand Now ✨ Get comprehensive property verification in minutes

Want to Buy or Sell Property Easily?

Skip the confusion. We'll handle verification, legal process, documentation, and handover so you can relax.

Call or WhatsApp us at
+91 9996 12 9996
and get your property journey started today!