Case law, Tamil Nadu land law

Appeal No. 58 of 2019

In force

The Tamil Nadu Real Estate Appellate Tribunal delivered its order in Appeal No. 58 of 2019 on 9 September 2020, concerning Sare Squires' challenge to the rejection of its complaint seeking registration of the Sare Squires Crescent ParC Dewy Terraces OMR Road project under the Real Estate (Regulation and Development) Act, 2016. The Tribunal examined whether completed sales and possession prevented the complaint, particularly where access, amenities and other alleged defects remained unresolved, but the supplied text does not include the final decision on the appeal.

CategoryTribunal and court orders
Effective1 January 2019
Pages15
StatusIn force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What the appeal concerns

The Tamil Nadu Real Estate Appellate Tribunal considered an appeal by Sare Squires, an association of apartment owners. Sare Shelters Project Private Limited was the promoter, and Dewy Terraces (Phase I) Flat Owners' Welfare Association was added as the second respondent.

Sare Squires had asked the Regulatory Authority to require registration of the Sare Squires Crescent ParC Dewy Terraces OMR Road project under the Real Estate (Regulation and Development) Act, 2016. The Regulatory Authority rejected the complaint as not maintainable after accepting the promoter's claim that construction and possession had been completed before the Act came into force.

Issues raised by apartment owners

Sare Squires alleged that important facilities and obligations remained incomplete or unresolved:

  • The community hall and shops had not been commenced.
  • The clubhouse was partly complete, unfit for use and partly occupied as the promoter's marketing office.
  • The sewage treatment plant was incomplete and inoperable.
  • There was no permanent water source, leaving owners dependent on tanker water at their cost.
  • Owners had lost access over the approved approach road.
  • The promoter had not produced evidence showing possession of M Block in Phase 4.

Dewy Terraces (Phase I) Flat Owners' Welfare Association supported the allegations concerning access to the main road.

Promoter's response

Sare Shelters Project Private Limited argued that construction was completed, possession was handed over and a completion certificate had been issued before the Act commenced. It also argued that responsibility for public roads rested with the local authority, and that it could not be responsible for defects in the original layout approval because it had purchased only part of the layout.

The promoter stated that maintenance of common amenities had been handed over. It also maintained that M Block was structurally complete and outside the Act.

Tribunal's legal approach

The Tamil Nadu Real Estate Appellate Tribunal framed two questions, whether the owners' complaint was maintainable and whether the appeal should be allowed. It stated that execution of conveyance deeds alone does not end a promoter's responsibilities, particularly regarding structural or other defects, essential services, completion or occupancy documentation, and common areas.

The Tribunal also reviewed official findings concerning the disputed approach road and noted the promoter's admission that part of the road involved temple land. The supplied text ends during this analysis and does not contain the Tribunal's final ruling.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Did the Tamil Nadu Real Estate Appellate Tribunal order the project to be registered?

The supplied text does not include the final ruling. It records the Tribunal's consideration of whether the complaint seeking registration was maintainable.

Does handing over possession automatically end the promoter's responsibilities?

No. The Tamil Nadu Real Estate Appellate Tribunal stated that executing conveyance deeds alone does not free a promoter from responsibility for structural or other defects covered by the Act.

What problems did the apartment owners raise?

They raised incomplete common amenities, an inoperable sewage treatment plant, lack of permanent water supply, problems with the approved access road, and lack of evidence that possession of M Block in Phase 4 had been handed over.

Why had the Regulatory Authority rejected the owners' complaint?

The Regulatory Authority accepted the promoter's preliminary argument that construction and possession had been completed before the Real Estate (Regulation and Development) Act, 2016 came into force, and therefore found the complaint not maintainable.