Appeal No. 57 of 2021
The Tamil Nadu Real Estate Appellate Tribunal issued Appeal No. 57 of 2021 on 22 November 2021 in a dispute between M/s. VGN Homes Private Limited and home buyer Mr. J. Jayaraj. The Tribunal considered whether an arbitration clause prevented the buyer from seeking remedies under the Real Estate Regulation And Development Act 2016, and whether the buyer could receive further interest and compensation after accepting delay compensation under the construction agreement. The supplied text ends before the Tribunal's final operative decision.
What the appeal concerns
The Tamil Nadu Real Estate Appellate Tribunal considered a promoter's appeal against an Adjudicating Officer's order dated 5 February 2021. The Adjudicating Officer had directed M/s. VGN Homes Private Limited to refund Rs.21,95,520 with interest at 10.05%, pay compensation of Rs.1,00,000, and pay litigation costs of Rs.25,000.
The promoter challenged the decision on several grounds:
- The construction agreement required disputes to be referred to an arbitrator appointed by the builder.
- The home buyer had allegedly delayed payments and was therefore not entitled to interest or compensation.
- Environmental clearance requirements had delayed completion and possession.
- The promoter had already paid Rs.55,050 as delay compensation under the construction agreement.
Arbitration and real estate remedies
The Tamil Nadu Real Estate Appellate Tribunal rejected the promoter's argument that the arbitration clause prevented the home buyer from approaching the real estate authority. Relying on the Supreme Court decision quoted in the document, the Tribunal found that a person who chooses a specific statutory remedy need not be sent to arbitration.
The Tribunal noted that the construction agreement did not specifically provide for a refund. It therefore found no error in the Adjudicating Officer entertaining the buyer's claims for refund and compensation under the Real Estate Regulation And Development Act 2016.
Earlier delay compensation
The Tamil Nadu Real Estate Appellate Tribunal found that the promoter had paid Rs.55,050 by cheque as delay compensation and that the home buyer had accepted it. The buyer had disclosed the payment in the complaint and proof affidavit.
The Tribunal stated that, because compensation had been paid and accepted under the construction agreement, a further claim for mental agony compensation and interest was not acceptable.
Alleged payment default and incomplete outcome
The Tamil Nadu Real Estate Appellate Tribunal found that the promoter produced no document showing delayed payment by the home buyer. The promoter had also not used the agreement clauses allowing termination or interest for payment default. A letter seeking Rs.73,721 as a handing over payment did not establish delay by the buyer.
The supplied text begins discussing the promoter's environmental clearance argument but ends before that issue is decided. It also does not include the final operative portion stating whether the appeal was allowed, dismissed or partly allowed.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
Can a builder force a home buyer into arbitration instead of a real estate authority proceeding?
Not in the circumstances considered here. The Tamil Nadu Real Estate Appellate Tribunal found that a buyer who chooses a specific statutory remedy can pursue that remedy despite an arbitration clause.
What amount had the Adjudicating Officer directed the promoter to refund?
The Adjudicating Officer directed a refund of Rs.21,95,520 with interest at 10.05%, compensation of Rs.1,00,000, and litigation costs of Rs.25,000.
Did the Tribunal accept that the home buyer had defaulted on payments?
No. The Tribunal found that the promoter had not produced documents proving delayed payment and had not invoked the contractual remedies available for payment default.
What was the final result of Appeal No. 57 of 2021?
The supplied text does not contain the final operative decision. It ends while the Tribunal is considering the environmental clearance argument.