Common Order in Appeal Nos.26 to 29 of 2023 and M.A.Nos.79 to 82 of 2023

In force

The Tamil Nadu Real Estate Appellate Tribunal (Tamil Nadu, Puducherry, Andaman & Nicobar Islands), in its common order in Appeal Nos.26 to 29 of 2023 and M.A.Nos.79 to 82 of 2023 delivered on 20 December 2023, dismissed appeals by M/s. Lancor Holdings Limited and upheld penalties for advertising and distributing brochures for an unregistered real estate project. The Tribunal treated M/s. Lancor Holdings Limited as a co-promoter and directed it to pay the balance penalty of Rs.70,000 in each case.

CategoryTribunal and court orders
Effective1 January 2023
Pages8
StatusIn force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What the case covers

The common order in Appeal Nos.26 to 29 of 2023 concerns the residential apartment project originally named "Jeyam Your Dream" at Adambakam Village, Alandur Taluk, Chengelpet District. The Tamil Nadu Real Estate Appellate Tribunal considered whether M/s. Lancor Holdings Limited violated Section 3(1) of the Real Estate (Regulation and Development) Act, 2016 by advertising and distributing brochures for the project when it was not registered with the Tamil Nadu Real Estate Regulatory Authority.

Section 3(1), as reproduced by the Tribunal, prevents a promoter from advertising, marketing, booking, selling, offering for sale or inviting purchases in a real estate project in a planning area without registration.

Background and affected parties

Jeayam Shelters Private Limited was the original promoter. The allottees had entered into separate construction agreements during 2011 and later sought refunds, interest and compensation after the project was allegedly not commenced even after six years.

M/s. Lancor Holdings Limited entered into a Memorandum of Understanding dated 8 August 2017 with the promoter, with the intention of taking over the project with stakeholder cooperation. The company renamed the project "LANCOR AURORA". It argued that the arrangement was never acted upon because all concerned parties did not cooperate and that brochures were given only to existing allottees for understanding.

Tribunal findings

The Tamil Nadu Real Estate Appellate Tribunal found that:

  • The project remained unregistered with the Tamil Nadu Real Estate Regulatory Authority.
  • M/s. Lancor Holdings Limited had admitted effecting an advertisement, although it claimed this was only to invite public claims and objections.
  • Jeayam Shelters Private Limited stated that M/s. Lancor Holdings Limited advertised for purchasers and released brochures dated 27 February 2018.
  • Renaming the project, advertising it and releasing brochures were sufficient to treat M/s. Lancor Holdings Limited as a co-promoter.
  • Whether the Memorandum of Understanding was ultimately acted upon was immaterial.

Result and practical effect

The common order dismissed all four appeals and upheld the penalty of Rs.1,00,000 in each case. Because M/s. Lancor Holdings Limited had already deposited Rs.30,000 in each case, it was directed to pay the remaining Rs.70,000 in each case to the learned Single Member of the Tamil Nadu Real Estate Regulatory Authority. The connected miscellaneous applications were also closed.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Can a company advertise a project that is not registered with the Tamil Nadu Real Estate Regulatory Authority?

The Tribunal held that issuing advertisements and distributing brochures for this unregistered project violated Section 3(1) of the Real Estate (Regulation and Development) Act, 2016.

Why was M/s. Lancor Holdings Limited treated as a co-promoter?

The Tribunal relied on the company entering into the Memorandum of Understanding, renaming the project "LANCOR AURORA", advertising it and releasing brochures soliciting purchasers.

Did it matter that the Memorandum of Understanding was allegedly never acted upon?

No. The Tribunal said that whether the Memorandum of Understanding dated 8 August 2017 was acted upon was immaterial, and noted that M/s. Lancor Holdings Limited had not taken steps to cancel it.

How much did M/s. Lancor Holdings Limited have to pay after the appeals were dismissed?

The penalty was Rs.1,00,000 in each case. After crediting the Rs.30,000 already deposited in each case, the Tribunal directed payment of the remaining Rs.70,000 in each case.