Minister P.K. Sekar Babu Inspects Kilambakkam New Bus Terminus Works
The Chennai Metropolitan Development Authority issued this project update on Minister P.K. Sekar Babu’s inspection of the final works at the new bus terminus in Kilambakkam, Chengalpattu district. It reports that the Kalaignar Centenary Bus Terminus, built to serve southbound buses and reduce congestion around Koyambedu, had reached 95 per cent completion and was being prepared for public use.
Purpose of the document
The Chennai Metropolitan Development Authority update records an inspection by Minister P.K. Sekar Babu, Minister and Chairman of the Chennai Metropolitan Development Authority and Minister for the Hindu Religious and Charitable Endowments Department. The inspection covered the final stage of the new bus terminus at Kilambakkam in Chengalpattu district, developed at an estimated cost of Rs.393.74 crore.
The update is a project status report. It does not state any change to land ownership, property title, planning permission or development controls.
Project status and purpose
The Kalaignar Centenary Bus Terminus was planned near Vandalur on approximately 59.86 acres. Its stated purpose is to accommodate buses travelling south and reduce traffic congestion in Koyambedu and surrounding parts of Chennai.
At the time reported:
- About 95 per cent of the works had been completed.
- The terminus was being prepared to open for public use in June.
- The source does not identify the year of the proposed June opening.
Bus and parking capacity
The Chennai Metropolitan Development Authority update describes the following capacity:
- 28.25 acres for suburban bus operations, with eight platforms and space for 226 buses, comprising 164 government buses and 62 omni buses.
- 7.40 acres for city bus operations, with 11 platforms and related arrival and departure facilities.
- A separate area for parking 144 buses that are not in service.
- Basement parking for 2,769 two wheelers and 324 four wheelers.
- Separate workshops for suburban and city buses.
- Space allocated for two fuel filling stations.
Passenger and site facilities
The main building has two basement levels, a ground floor and a first floor. Facilities listed in the update include:
- 53 shops, two restaurants and two fast food outlets on the ground floor.
- 46 shops and one restaurant on the first floor.
- An emergency treatment centre, pharmacy, luggage room, breastfeeding room, ticketing area and cash machine.
- Separate passenger rest rooms and toilets for men and women.
- Passenger lifts, service lifts and escalators.
- Protected drinking water, surveillance facilities and staff rest rooms.
- Stormwater drains, rainwater storage, sewage pumping and treatment systems, drinking water treatment, a power substation and diesel generators.
- Streetlights, high mast lights and a landscaped green park.
Who may be affected
The project is relevant to passengers, government and omni bus operators, city bus services, prospective shop users and people travelling through Koyambedu, Vandalur and Kilambakkam. The update provides operational and construction information, but it does not announce property acquisition or impose obligations on nearby landowners.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
Does this document change my property rights near Kilambakkam?
No change to property ownership, title, planning permission or development controls is stated. The document reports the construction status and facilities of the bus terminus.
Why was the Kilambakkam bus terminus developed?
The stated purpose is to serve buses travelling south and reduce traffic congestion in Koyambedu and surrounding areas of Chennai.
How much parking is provided at the terminus?
The update lists basement parking for 2,769 two wheelers and 324 four wheelers. It also identifies space for 226 suburban buses and a separate area for 144 buses that are not in service.
Was the terminus open when the inspection was reported?
The update says 95 per cent of the works had been completed and the terminus was being prepared to open for public use in June. It does not provide the year of that proposed opening.