No. 2015/LML-1/19/2, Procedure for issue of No Objection Certificate for construction or redevelopment of Government and private building on land adjoining railway boundary
The Government of India, Ministry of Railways (Railway Board), issued letter No. 2015/LML-1/19/2 dated 25 June 2015 to standardise the procedure for granting a Railway No Objection Certificate for Government and private construction or redevelopment adjoining a railway boundary. A Railway No Objection Certificate is required for building construction within 30 metres of the railway boundary, with the precise open space assessed according to local conditions and railway safety needs.
What the guidance governs
Railway Board letter No. 2015/LML-1/19/2 applies to Government and private buildings on land adjoining a railway boundary. Its purpose is to protect railway land and operations by preventing encroachment and avoiding easement claims over railway land, including rights of way and rights to discharge sullage or storm water.
The Indian Railways Works Manual indicates approximately 30 metres of open space between the railway boundary and the nearest edge of a building, although the exact space depends on local conditions. In cities and towns where land is valuable, the guidance recognises that leaving a large vacant area may not be practical. The space must still allow future road access and drainage outside railway land.
Who is affected
The Railway No Objection Certificate procedure affects:
- Owners or applicants proposing Government or private construction or redevelopment near railway land.
- State Government and local authorities forwarding applications to the concerned railway divisional office.
- Railway field units, divisions and headquarters responsible for verification and approval.
- Applicants proposing high rise buildings or basements involving deep excavation near railway tracks.
Application documents and checks
An applicant must provide a request forwarded by the State Government or local authority, together with:
- Clear title to the land, supported by all related documents.
- A detailed building drawing showing the complete layout, height, width and length.
- A structural stability certificate from a civil or structural engineer.
Railway field units must verify the site, railway land width, plot distance from the railway boundary, rail level and ground level. The plot must be identified by reference to a kilometre post and permanent structures. A drawing must also show drainage, building access, dimensions and the distance from the railway boundary.
Approval and safety requirements
The divisional office scrutinises the proposal after field verification and may consult construction units to confirm that the land is not under acquisition. A proposal approved by the Divisional Railway Manager is sent to headquarters for approval before the division issues the certificate.
Railway review must consider train safety, land boundaries, road availability and waste disposal. Sewage, sullage water and septic tank discharge must be kept away from railway land. High rise buildings and basements may be subject to railway supervision or inspection during construction and throughout the building's lifetime. The stated time limit for granting the certificate is 60 days.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
Do I need a Railway No Objection Certificate to build near a railway boundary?
A Railway No Objection Certificate is required for construction within 30 metres of the railway boundary. The precise open space required is assessed according to local conditions.
What documents must accompany my application?
The request must be forwarded by the State Government or local authority and include clear land title documents, detailed building drawings and a structural stability certificate from a civil or structural engineer.
How long does the railway have to grant the certificate?
Railway Board letter No. 2015/LML-1/19/2 states a total time limit of 60 days for granting the No Objection Certificate.
Are basements or high rise buildings near railway tracks subject to extra checks?
Yes. The railway must examine the drawings and construction method where deep digging is involved and may require railway supervision or inspection during construction and during the building's lifetime.