Amendments to the Tamil Nadu Combined Development and Building Rules, 2019 (2023)

The Housing and Urban Development Department of the Government of Tamil Nadu issued G.O. Ms. No. 1, Housing and Urban Development [UD4(1)], dated 2 January 2023, to amend rule 45 of the Tamil Nadu Combined Development and Building Rules, 2019. The amendments set minimum separation requirements for Wind Electricity Generators, prohibit their erection within 500 metres of a dwelling unit, and require micro siting plans and technical specifications to be certified by the Tamil Nadu Generation and Distribution Corporation Limited.

Category
Gazette notifications
Effective
1 January 2023
Pages
2
Status
In force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What the amendment governs

G.O. Ms. No. 1, Housing and Urban Development [UD4(1)], dated 2 January 2023, issued by the Housing and Urban Development Department of the Government of Tamil Nadu, changes requirements for the placement and approval of Wind Electricity Generators under rule 45 of the Tamil Nadu Combined Development and Building Rules, 2019.

The amendment was published in the Tamil Nadu Government Gazette Extraordinary on 2 January 2023. It was made by the Governor of Tamil Nadu using powers under the town and country planning, municipal, panchayat and city municipal corporation laws listed in the notification.

Who may be affected

The amended Tamil Nadu Combined Development and Building Rules, 2019 may affect:

  • Owners or developers proposing to install or erect a Wind Electricity Generator.
  • Owners or occupiers of dwelling units located near a proposed Wind Electricity Generator site.
  • Persons assessing land near public roads, railway tracks, highways, high voltage electric lines, buildings or public institutions.
  • Professionals preparing plans showing the micro siting, development, installation, erection or operation of Wind Electricity Generators.

Minimum separation requirements

The amended rule 45 requires the minimum distance between a Wind Electricity Generator and specified nearby features to be calculated using the following formula:

  • Tower height or hub height, in metres.
  • Plus half the blade or rotor diameter, in metres.
  • Plus 5 metres.

This calculated distance must be maintained from public roads, railway tracks, highways, high voltage electric lines, buildings and public institutions.

A separate restriction states that a Wind Electricity Generator must not be erected within 500 metres of any dwelling unit. The notification does not provide a separate measurement method for this 500 metre restriction.

Certification of plans

The amended Tamil Nadu Combined Development and Building Rules, 2019 require the plan showing the micro siting of a Wind Electricity Generator within a site to be certified by the Tamil Nadu Generation and Distribution Corporation Limited.

The certification requirement also covers the specifications relating to the development, installation, erection and operation of the Wind Electricity Generator.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Can a Wind Electricity Generator be erected within 500 metres of my house?

No, if the house is a dwelling unit. The amended rule states that a Wind Electricity Generator must not be erected within 500 metres of any dwelling unit.

How is the required distance from a public road or building calculated?

The minimum distance is the tower height or hub height, plus half the blade or rotor diameter, plus 5 metres. The same formula applies to public roads, railway tracks, highways, high voltage electric lines, buildings and public institutions.

Who must certify the micro siting plan for a Wind Electricity Generator?

The Tamil Nadu Generation and Distribution Corporation Limited must certify the micro siting plan and the specifications relating to development, installation, erection and operation.

Does the 500 metre dwelling restriction replace the other distance formula?

The notification states both requirements separately. It adds the 500 metre restriction for dwelling units while also prescribing the height and rotor based distance for roads, railway tracks, highways, high voltage electric lines, buildings and public institutions.