G.O.Ms. No.8, Withdrawal from Acquisition of Lands, 2022
The Tamil Nadu Energy Department issued G.O.Ms. No.8, Energy (B1), dated 11 February 2022, withdrawing specified extents of land in Vendipalayam Village, Erode Taluk, Erode District, from acquisition for industrial purposes. The lands had been covered by an Energy Department acquisition notice published on 8 March 2019, but actual possession had not been taken by or on behalf of the Government.
What the notification does
G.O.Ms. No.8, Energy (B1), issued by the Tamil Nadu Energy Department on 11 February 2022, withdraws two specified land extents in Vendipalayam Village, Erode Taluk, Erode District, from acquisition under the Tamil Nadu Acquisition of Land for Industrial Purposes Act, 1997.
The affected lands were included in Energy Department Notification No.II(2)/EGY/212(k)/2019, published in the Tamil Nadu Government Gazette Extraordinary on 8 March 2019. The withdrawal applies because actual possession of these lands had not been taken by or on behalf of the Government.
Lands covered
The schedule identifies the following land:
- R.S. No. 23/1, later shown as subdivision 23/1B, has a total extent of 0.74.00 hectares. An extent of 0.34.00 hectares is withdrawn from acquisition.
- R.S. No. 23/2, later shown as subdivision 23/2B, has a total extent of 0.88.00 hectares. An extent of 0.20.00 hectares is withdrawn from acquisition.
- Both entries are classified as Ryot Nanjai.
- The listed land owners or persons interested are Shankar, son of Subramaniyam, and Sathesh, son of Subramaniyam.
Who is affected
G.O.Ms. No.8 directly concerns the listed owners or interested persons and anyone dealing with the specified extents in subdivisions 23/1B and 23/2B. Buyers, owners and professionals should note that the withdrawal is limited to the extents recorded in the schedule, rather than the full total extent shown for each survey number.
Key points for land records
- The location is Vendipalayam Village in Erode Taluk and Erode District.
- The notification withdraws the scheduled extents from the acquisition process begun through the 2019 Energy Department notification.
- The schedule records both the earlier survey numbers and the later subdivision numbers.
- The stated reason relevant to the withdrawal is that the Government had not taken actual possession of the scheduled lands.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
Does the notification withdraw all of R.S. Nos. 23/1 and 23/2 from acquisition?
No. It withdraws 0.34.00 hectares from R.S. No. 23/1, subdivision 23/1B, and 0.20.00 hectares from R.S. No. 23/2, subdivision 23/2B.
Where are the lands covered by G.O.Ms. No.8 located?
They are in Vendipalayam Village, Erode Taluk, Erode District.
Why could the Government withdraw these lands from acquisition?
The notification states that actual possession had not been taken by or on behalf of the Government.
Who is listed as the owner or person interested in the land?
The schedule lists Shankar, son of Subramaniyam, and Sathesh, son of Subramaniyam.