Acquisition of Lands, G.O.Ms. Nos. 67 and 68, Energy (C1), 2011

The Tamil Nadu Energy Department issued G.O.Ms. No. 67, Energy (C1), dated 30 August 2011, and G.O.Ms. No. 68, Energy (C1), dated 30 August 2011, concerning land acquisition for two power projects. The first acquires specified land in Vilangadu Village, Cheyyur Taluk, Kancheepuram District, for an Ultra Mega Power Project, while the second gives notice of proposed acquisition in Somenahalli and Pangunatham Villages, Dharmapuri Taluk, Dharmapuri District, for a Power Grid Corporation of India Limited substation and applies an urgency procedure.

Category
Gazette notifications
Pages
8
Status
In force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What the notifications cover

The Tamil Nadu Energy Department published two land acquisition notifications in the Tamil Nadu Government Gazette Extraordinary on 30 August 2011. They concern specific survey fields identified by survey number, ownership, patta details, boundaries and area.

Vilangadu Village acquisition

G.O.Ms. No. 67, Energy (C1), dated 30 August 2011, acquires land in Block 17 of Vilangadu Village, Cheyyur Taluk, Kancheepuram District, for forming an Ultra Mega Power Project.

Key provisions include:

  • The acquired land measures approximately 11.16 acres, or a scheduled total of 4.52.5 hectares.
  • The affected survey numbers are 12/1A, 12/1B, 12/1C, 12/1D, 12/1E and 13.
  • The schedule identifies the recorded owners, patta numbers, adjoining survey fields and individual areas.
  • Compensation is to be paid from funds controlled or managed by Coastal Tamil Nadu Power Limited, New Delhi.
  • The notification states that causes shown by owners or other interested persons were considered before acquisition.
  • The land plan may be inspected during office hours at the office of the Special Tahsildar (Land Acquisition), Unit V, Ultra Mega Power Project, Cheyyur, Kancheepuram.

Dharmapuri substation acquisition process

G.O.Ms. No. 68, Energy (C1), dated 30 August 2011, gives notice that land in Somenahalli and Pangunatham Villages, Dharmapuri Taluk, Dharmapuri District, is needed for construction of a 765/400 K.V. Power Sub-Station by Power Grid Corporation of India Limited.

Key provisions include:

  • The Governor directs acquisition because immediate possession is considered necessary.
  • The Sub-Collector, Dharmapuri, is authorised to exercise the stated acquisition powers with staff and workmen.
  • The Sub-Collector, Dharmapuri, is appointed to perform the functions of Collector for the acquisition.
  • Because of urgency, the notification directs that the procedure under Section 5-A of the Land Acquisition Act, 1894, will not apply.
  • The schedule lists numerous dry ryotwari lands by survey subdivision, recorded owner, boundaries and area.

Who should check the schedules

Owners, buyers, lenders and professionals dealing with land in the named villages should compare the property survey number and subdivision with the Gazette schedules. A matching survey number may indicate that the land is acquired or included in an acquisition process for the relevant power project.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Which land in Vilangadu Village was acquired for the Ultra Mega Power Project?

The notification covers survey numbers 12/1A, 12/1B, 12/1C, 12/1D, 12/1E and 13 in Block 17 of Vilangadu Village. The scheduled total is 4.52.5 hectares, described as approximately 11.16 acres.

Where can I inspect the plan for the Vilangadu lands?

The plan is available during office hours at the office of the Special Tahsildar (Land Acquisition), Unit V, Ultra Mega Power Project, Cheyyur, Kancheepuram.

What project is the Dharmapuri land required for?

The land in Somenahalli and Pangunatham Villages is required for construction of a 765/400 K.V. Power Sub-Station by Power Grid Corporation of India Limited.

Does the Dharmapuri notification use an urgency procedure?

Yes. It directs immediate acquisition and states that, because of urgency, the procedure under Section 5-A of the Land Acquisition Act, 1894, will not apply.