G.O. Ms. No. 351, Acquisition of Lands, 2010
The Government of Tamil Nadu, Transport Department, issued G.O. Ms. No. 351, Transport (I.1), dated 29th November 2010, to notify the urgent acquisition of five land parcels totalling 0.55.5 hectare in Kumaripalayam Village, Namakkal Taluk and District, for a road over bridge approach connected with the Salem-Karur Broad Gauge Railway Line Project. The notification authorises the Special Tahsildar (Land Acquisition), Unit-I, Namakkal, appoints that officer to perform the Collector's functions, and directs that Section 5-A of the Land Acquisition Act, 1894 will not apply because of urgency.
What the notification does
G.O. Ms. No. 351, Transport (I.1), dated 29th November 2010, was issued by the Government of Tamil Nadu, Transport Department, under the Land Acquisition Act, 1894. It identifies land required for the road over bridge approach area arising from the Salem-Karur Broad Gauge Railway Line Project.
The notification states that immediate possession is necessary and directs acquisition under sub-section (2) of Section 17. Because of the urgency, the Governor of Tamil Nadu directs that Section 5-A will not apply to the case.
Location and land covered
The acquisition covers five parts of government dry land in No. 87, Kumaripalayam Village, Namakkal Taluk, Namakkal District. The total stated extent is 0.55.5 hectare.
The scheduled parcels are:
- Survey No. 460-3B2 (part), patta No. 1408, belonging to Ramasamy, son of Perumal, measuring 0.32.5 hectare.
- Survey No. 463-2B (part), patta No. 689, belonging to Muthusamy, son of Palaniyandi Gounder, measuring 0.02.5 hectare.
- Survey No. 463-3B2 (part), patta No. 109, belonging to Karupayee, wife of Karuppannan Gounder, measuring 0.05.5 hectare.
- Survey No. 463-5 (part), patta No. 163, belonging to Kaliannan, son of Veerappa Gounder, measuring 0.04.5 hectare.
- Survey No. 463-6 (part), patta No. 110, belonging to Jawahar, son of Karuppannan, measuring 0.10.5 hectare.
The schedule also gives the boundary survey numbers for each parcel.
Authority given to officials
G.O. Ms. No. 351 authorises the Special Tahsildar (Land Acquisition), Unit-I, Salem-Karur Broad Gauge Railway Line Project, Namakkal, together with staff and workmen, to exercise the specified statutory powers. The Special Tahsildar is also appointed to perform the functions of the Collector under the Land Acquisition Act, 1894.
Who is affected
The notification directly concerns the named patta holders and the listed parts of the five survey numbers. A buyer, owner or professional dealing with land in Kumaripalayam Village should compare the survey number, subdivision, patta number, extent and boundaries with the schedule to determine whether a property is included.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
What public project is the land being acquired for?
The land is required for the road over bridge approach area connected with the formation of the Salem-Karur Broad Gauge Railway Line Project.
How much land does the notification cover?
The schedule states a total extent of 0.55.5 hectare across five land parcels.
Which village and survey numbers are affected?
The land is in No. 87, Kumaripalayam Village, Namakkal Taluk and District. The affected subdivisions are Survey Nos. 460-3B2, 463-2B, 463-3B2, 463-5 and 463-6, each only in part.
Does Section 5-A of the Land Acquisition Act apply?
No. The Governor of Tamil Nadu directed that Section 5-A would not apply because of the urgency of the case.