O.O.No.30/2024, Office Order on Transfer of SIPCOT Leasehold Rights

In force

The State Industrial Promotion Corporation of Tamil Nadu Limited issued Office Order Number 30 of 2024, dated 20 December 2024, changing the conditions for change in management or transfer of leasehold rights for plots allotted in SIPCOT Industrial Parks. It sets deadlines for payment and registration of a Modified Lease Deed, permits a further extension in suitable cases, and fixes project implementation periods for the new management.

CategoryIndustrial land
Effective1 January 2024
Pages2
StatusIn force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What the office order governs

Office Order Number 30 of 2024, dated 20 December 2024, was issued by the State Industrial Promotion Corporation of Tamil Nadu Limited. It applies when an allotted plot in a SIPCOT Industrial Park undergoes a change in management or a transfer of leasehold rights.

The changes affect the transferor, the transferee or new management, and units whose projects must be implemented after a Modified Lease Deed is executed and registered.

Payment and lease deed deadlines

The State Industrial Promotion Corporation of Tamil Nadu Limited has approved the following conditions:

  • The Differential Land Cost and Processing Fee must be paid within 30 days from the date on which the change in management or transfer of leasehold rights is approved.
  • The payment may be made by the transferor or transferee.
  • Any applicable interest becomes payable if payment is delayed.
  • The transferee must execute and register the Modified Lease Deed within 45 days from the date of payment of the Differential Land Cost and Processing Fee, together with any applicable interest for delayed payment.
  • The Managing Director may grant an additional 45 days for execution and registration of the Modified Lease Deed, based on the merits of the case and without penalty.
  • Any further extension must follow the delegation of powers given in Office Order Number 21 of 2022, dated 8 July 2022.

Project implementation period

The implementation period is calculated from the execution or registration of the Modified Lease Deed.

A 12 month period applies to:

  • Units that have not commenced commercial production.
  • Units functioning for more than five years from commencement of commercial production.
  • Units functioning for less than five years from commencement of commercial production.
  • Stock exchange listed public limited companies that have commenced commercial production.

A 24 month period applies to:

  • Revival of sick units under schemes approved by Banks, FI, BIFR, NCLT or other legal forums.
  • Asset sales by an Official Liquidator, Court or NCLT.
  • Asset sales by Banks, FI, listed NBFC or ARC, whether or not an NOC was issued for mortgaging the leasehold rights.
  • Joint venture companies of TIDCO, ELCOT, TIDEL, SIPCOT or other government agencies where the relevant government agency board has approved the shareholding change.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

How long do I have to pay after SIPCOT approves a transfer of leasehold rights?

The Differential Land Cost and Processing Fee must be paid within 30 days from the approval date. Applicable interest may be charged for delayed payment.

When must the new management register the Modified Lease Deed?

The transferee must execute and register it within 45 days from payment of the Differential Land Cost and Processing Fee, including any applicable interest for delayed payment.

Can SIPCOT extend the time for registering the Modified Lease Deed?

The Managing Director may grant an additional 45 days based on the merits of the case, without penalty. Any further extension is governed by Office Order Number 21 of 2022, dated 8 July 2022.

When does the project implementation period begin for the transferee?

It begins from the date of execution or registration of the Modified Lease Deed. Depending on the category of the unit or transaction, the period is 12 months or 24 months.