DRAFT ALLOTMENT ORDER A & B DISTRICTS
The Draft Allotment Order A & B Districts is a plot lease allotment template issued by the State Industries Promotion Corporation of Tamilnadu Ltd. for industrial parks in A and B districts, reflecting modifications approved by its Board on 16 May 2024. It sets out payment, construction, project implementation, site use and approval conditions for a ninety-nine-year industrial plot lease. The reference number and issue date are left blank in the template.
What the document covers
The Draft Allotment Order A & B Districts is intended for companies, firms and proprietary concerns receiving plots in industrial parks managed by the State Industries Promotion Corporation of Tamilnadu Ltd. Each plot is allotted on a ninety-nine-year lease for the manufacture stated in the completed allotment order.
The final plot extent may change after measurement when possession is handed over. The total amount payable will be adjusted accordingly.
Main deadlines
An allottee must:
- Accept the allotment within 7 days and confirm acceptance of the prevailing allotment orders and circulars published on the corporation's website.
- Pay the full amount specified in the allotment order within 30 days.
- Execute and register the lease deed within 45 days after payment.
- Take possession in its existing condition within 15 days after execution or registration of the lease deed.
- Complete construction and implement the project within 36 months after registration of the lease deed.
Failure to accept or pay on time causes automatic cancellation and forfeiture of the initial deposit. Late execution of the lease deed attracts a penalty of 0.5% of the prevailing plot cost for every 30 days of delay. Failure to implement the project can result in cancellation and resumption of the plot, unless an extension is granted with a penalty under the prevailing policy.
Payments and continuing costs
The allottee may have to pay plot cost, frontage charges, water supply capital cost, caution deposit and advance lease rent. The interest-free caution deposit is refundable if the project is implemented within the required time, subject to the stated exception for qualifying Mega Projects.
The State Industries Promotion Corporation of Tamilnadu Ltd. may also collect proportionate additional development expenses, annual maintenance charges and 50% of project costs under the Participatory Infrastructure Development Programme. The allottee is responsible for applicable taxes, assessments, electricity connections and other support infrastructure costs.
Construction and use restrictions
Buildings must comply with local body requirements, development controls, building regulations, environmental laws and other applicable requirements. The plot must retain an open setback of at least 5 metres on every side. Temporary structures are allowed only during construction or future reconstruction, and katcha or inflammable construction is prohibited.
Wells, bore wells and tube wells require prior permission. The corporation may inspect the plot and use the 5 metre strip for common pipelines, bore wells or facilities without paying compensation or rent.
Changes requiring approval
The allottee must obtain prior approval from the State Industries Promotion Corporation of Tamilnadu Ltd. for changes in constitution or management, and for transfer of leasehold rights in whole or in part. Applicable charges under the prevailing policy must also be paid.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
How long is the industrial plot lease?
The plot is allotted on lease for ninety-nine years for establishing the industrial unit described in the completed allotment order.
What happens if I do not pay the allotment amount within 30 days?
The allotment is automatically cancelled, and the initial deposit paid for the allotted extent is forfeited.
Can I drill a bore well on the allotted plot?
Only with prior permission from the State Industries Promotion Corporation of Tamilnadu Ltd. An existing well may have to be closed when common water supply begins, and an existing bore well must remain under the corporation's control.
Can I transfer the industrial plot lease to another person or company?
Transfer of leasehold rights, whether for the whole plot or part of it, requires prior approval from the State Industries Promotion Corporation of Tamilnadu Ltd. Applicable charges under its prevailing policy must be paid.