G.O.(D)No.396, Release of funds for Coimbatore Ukkadam Phase III

The Municipal Administration and Water Supply Department issued Government Order G.O.(D)No.396 dated 25 September 2017, sanctioning and releasing Rs.42,72,26,000 for the Tamil Nadu Slum Clearance Board project at Ukkadam, Coimbatore. The amount comprises a Government of India share of Rs.1,814.54 lakh and a Government of Tamil Nadu matching share of Rs.2,457.72 lakh as the third and final instalment under the Jawaharlal Nehru National Urban Renewal Mission.

Category
Town and country planning orders
Pages
4
Status
In force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What the government order does

Government Order G.O.(D)No.396 dated 25 September 2017, issued by the Municipal Administration and Water Supply Department, approves the Commissioner of Municipal Administration's request to release Rs.42,72,26,000 for the Ukkadam Phase III housing project in Coimbatore. The release consists of Rs.1,814.54 lakh as the Government of India share and Rs.2,457.72 lakh as the Government of Tamil Nadu matching share.

The document describes the payment as the third and final instalment under the Basic Services of Urban Poor scheme of the Jawaharlal Nehru National Urban Renewal Mission. The sanction paragraph also refers to projects under the Integrated Housing and Slum Development Programme Scheme.

Project covered

Government Order G.O.(D)No.396 records the following project details:

  • Implementing agency: Tamil Nadu Slum Clearance Board.
  • Location and phase: Ukkadam Phase III, Coimbatore Corporation.
  • Original approval: 9,600 dwelling units, with a total project cost of Rs.18,480.89 lakh.
  • Revised approval: 7,048 dwelling units, with a total project cost of Rs.39,171.59 lakh.
  • Central share previously released: Rs.4,554.17 lakh.
  • State share previously released: Rs.4,468.46 lakh.
  • Current release: Rs.4,272.26 lakh in total.

The approved Government of India instalment reflects a deduction of Rs.2,306.00 lakh for housing and proportionate infrastructure relating to 2,552 dwelling units described as non starters.

Funding and administration

Government Order G.O.(D)No.396 allocates the sanctioned expenditure as follows:

  • General Component, 74 percent: Rs.31,61,47,240.
  • Special Component, 26 percent: Rs.11,10,78,760.
  • The expenditure is to be met from the State Infrastructure and Amenities Fund through accounting adjustments.
  • The Commissioner of Municipal Administration is authorised to draw the amount and disburse it to the implementing agency.
  • The expenditure was to be included in the revised financial arrangements and Supplementary Estimates for 2017 to 2018.
  • Expenditure details were to be furnished to the Director of Town and Country Planning and the Accountant General.

Relevance to property holders

Government Order G.O.(D)No.396 is a project funding sanction. It does not record a land acquisition, change of land use, planning permission, ownership transfer or individual allotment of a dwelling. Its direct administrative effect is on the Commissioner of Municipal Administration and the Tamil Nadu Slum Clearance Board as the implementing agency.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Does G.O.(D)No.396 change the land use or ownership of property at Ukkadam?

No land use change or ownership transfer is recorded. Government Order G.O.(D)No.396 sanctions funding for the Ukkadam Phase III housing project.

How much money was released for the Ukkadam Phase III project?

The total release was Rs.42,72,26,000, comprising Rs.1,814.54 lakh from the Government of India and Rs.2,457.72 lakh as the Government of Tamil Nadu matching share.

How many dwelling units does the document cover?

The original approval was for 9,600 dwelling units. The revised approval shown in the document is for 7,048 dwelling units.

Who is responsible for implementing the project?

The Tamil Nadu Slum Clearance Board is identified as the implementing agency for Ukkadam Phase III. The Commissioner of Municipal Administration is authorised to draw and disburse the sanctioned amount.