Official guidance, Tamil Nadu land law

G.O. (D) No. 142, Sanganoor Pallam Development Project, 2025

In force

The Municipal Administration and Water Supply (MA.NA.4) Department issued G.O. (D) No. 142 dated 19 March 2025, permitting Coimbatore City Municipal Corporation to use ₹3.12 crore in savings from the Sanganoor Pallam development project for the dedicated Valankulam surplus water canal project. The funding will support completion of the remaining 265 metres of canal on Trichy Road and restoration of the road damaged during drainage construction.

CategoryTown and country planning orders
Pages3
StatusIn force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What the government has approved

G.O. (D) No. 142 dated 19 March 2025 permits Coimbatore City Municipal Corporation to transfer ₹3.12 crore from savings available under the Sanganoor Pallam development project. The money will be used for the dedicated canal intended to carry surplus water from Valankulam, along Trichy Road, into Sanganoor Pallam.

The transferred amount comes from the ₹3.50 crore expected to remain as savings in the Infrastructure and Amenities Fund project for 2020 to 2021. It will be used for the canal project funded under the Infrastructure and Amenities Fund schemes for 2021 to 2022 and 2022 to 2023.

Projects and works covered

The Sanganoor Pallam development project covers the stretch from Mettupalayam Road to Sathy Road in Coimbatore. Administrative approval had been given for ₹49 crore, and expenditure was estimated at about ₹46 crore, leaving expected savings of ₹3.50 crore.

The Valankulam surplus water canal project has the following position:

  • Total approved estimate is ₹9 crore.
  • Total canal length is 1,730 metres.
  • Work has been completed for 1,465 metres.
  • The remaining canal length is 265 metres.
  • An additional ₹3.12 crore is required to complete the work and restore the affected road.

Why additional funding is required

The canal was initially planned along the side of Trichy Road beside the existing storm water drain. Drinking water pipes, underground sewer pipes, electricity cables and other cables made construction at the roadside impractical.

The design was therefore changed to place the flood water canal through the centre of Trichy Road. The drainage design was revised to IRC standards in accordance with National Highways Department guidance. The additional funding covers completion of the remaining canal and restoration of the National Highways Department road damaged for the drainage work.

Who may be affected

G.O. (D) No. 142 dated 19 March 2025 concerns municipal drainage construction around Trichy Road, Valankulam and Sanganoor Pallam. Residents, owners and road users in these areas may encounter the canal completion and road restoration works. The document does not record any land acquisition, ownership transfer or change of land use.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Does this government order acquire private land or change my property title?

No land acquisition, ownership transfer or title change is recorded in the source text. The approval concerns the use of project savings for canal completion and road restoration.

How much additional money has been approved for the canal?

The Municipal Administration and Water Supply (MA.NA.4) Department has permitted ₹3.12 crore to be used from ₹3.50 crore in expected savings under the Sanganoor Pallam development project.

How much of the Valankulam surplus water canal remains unfinished?

Of the total 1,730 metres, 1,465 metres has been completed and 265 metres remains.

Why was the canal moved to the centre of Trichy Road?

Construction along the roadside was not possible because drinking water pipes, underground sewer pipes, electricity cables and other cables caused obstructions. The canal design was revised for construction through the road centre.