official guidance

Common Schedule of Plinth Area Rates for the Valuation of Buildings for Rental Calculation Purpose by PWD and for the Purpose of Collection of Stamp Duty by Registration Department during the year 2021-2022

The Government of Tamil Nadu Public Works Department, Office of the Engineer-in-Chief (Buildings) and Chief Engineer (Buildings), Chennai Region, issued Proceedings No. HDO (B) / 65325 / 2001 dated 14 September 2021, approving statewide plinth area rates for building valuation. The rates applied from 16 September 2021 to 15 September 2022 for Public Works Department rental calculations and Registration Department stamp duty collection, and excluded the cost of land.

Category
Rate schedules
Effective
1 January 2021
Pages
33
Status
In force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What the schedule governs

Proceedings No. HDO (B) / 65325 / 2001 dated 14 September 2021 approved a common schedule for valuing buildings by plinth area and construction type. It served two purposes:

  • Calculating rent for buildings through the Government of Tamil Nadu Public Works Department.
  • Valuing buildings for stamp duty collection by the Registration Department.

The approved rates operated for one year, from 16 September 2021 to 15 September 2022. Public Works Department Chief Engineers, Superintending Engineers and Executive Engineers were instructed to use them for building rental calculations.

Who may be affected

The schedule may be relevant to owners of private buildings occupied by government offices, because Public Works Department officers use it when calculating or renewing rent. It may also be relevant to buyers, sellers and property professionals where the Registration Department needs to value the building component for stamp duty.

The valuation is based on the building's plinth area and construction type. The schedule expressly excludes the cost of land.

Key provisions

  • The rates apply throughout Tamil Nadu, subject to location based additions.
  • An additional 20 percent applies within Chennai Corporation limits and the belt extending 32 kilometres around those limits.
  • An additional 15 percent applies within Coimbatore, Erode and Tiruppur Corporation limits.
  • An additional 10 percent applies within the Corporation limits of Trichy, Madurai, Salem, Tirunelveli, Thoothukudi, Vellore, Thanjavur, Dindigul, Hosur, Nagercoil and Avadi.
  • An additional 5 percent applies within all municipal limits.
  • An additional 10 percent applies to buildings in the Nilgiris, Kodaikanal and Yercaud Hills.
  • These location additions apply to the rates listed under items I to XV.

Building categories

The schedule separates load bearing structures from framed structures. A load bearing structure uses stone or brick masonry walls to carry slab loads without reinforced cement concrete or steel columns. A framed structure uses reinforced cement concrete or steel columns and beams to carry slab loads.

The listed categories include several classes of load bearing and reinforced cement concrete framed buildings, godowns, thatched or tiled roofs, garages, miscellaneous items, services and electrical items. Rates can vary by roof type, floor and construction materials.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Does this schedule include the value of the land?

No. The schedule states that building valuation by plinth area excludes the cost of land.

Was the schedule valid throughout Tamil Nadu?

Yes. The approved rates applied across the state, with specified percentage additions for certain corporations, municipalities, the Chennai surrounding belt and selected hill areas.

How long were these rates in operation?

They operated from 16 September 2021 to 15 September 2022.

Could these rates affect stamp duty on a property transaction?

Yes. The schedule was approved for Registration Department building valuation for stamp duty collection, as well as for Public Works Department rental calculations.