Common Schedule of Plinth Area Rates for the Valuation of Buildings for Rental Calculation Purpose by PWD and for the Purpose of Collection of Stamp Duty by Registration Department during the Year 2025-2026

The Government of Tamil Nadu Public Works Department, through Proceedings No. HDO (B) / 65325 / 2001 dated 7 August 2025, approved statewide plinth area rates for valuing buildings for Public Works Department rental calculations and Registration Department stamp duty collection. The rates apply from 16 August 2025 to 15 August 2026, exclude land cost and include location based additions for specified cities, municipalities and hill areas.

Category
Registration and stamp duty
Effective
1 January 2025
Pages
32
Status
In force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What the schedule does

The Common Schedule of Plinth Area Rates issued by the Government of Tamil Nadu Public Works Department sets rates per square metre for valuing different types of buildings. The valuation is used for calculating rent by the Public Works Department and for collecting stamp duty by the Registration Department. Proceedings No. HDO (B) / 65325 / 2001 dated 7 August 2025 approves the rates for use from 16 August 2025 to 15 August 2026.

The rates apply across Tamil Nadu and cover building value based on plinth area. The cost of land is excluded.

Who may be affected

The Common Schedule of Plinth Area Rates may affect owners whose private buildings are rented or considered for rent by government offices. It may also affect property buyers, sellers and professionals where the Registration Department uses building valuation for stamp duty collection.

The schedule was circulated to Public Works Department engineering officers and Registration Department officials, including the Inspector General of Registration, district registrars and sub-registrars.

Main provisions

The approved schedule:

  • Classifies buildings by construction, including several classes of load bearing structures and reinforced cement concrete framed structures.
  • Includes godowns, older buildings using mud mortar and country wood, thatched or tiled roofs, garages, miscellaneous items, external and internal services, and electrical items.
  • Defines a load bearing structure as one where stone or brick masonry walls carry slab loads without reinforced cement concrete or steel columns.
  • Defines a framed structure as one where reinforced cement concrete or steel columns and beams carry slab loads.
  • Allows rates for items not covered in the schedule to be taken from the approved Common Schedule of Rates for 2025-2026 or approved plinth area rates for rough cost estimates for building schemes for that year.

Location based additions

For rates listed under items I to XV, the Common Schedule of Plinth Area Rates requires additions of:

  • 20 per cent within Chennai Corporation limits and the belt extending 32 kilometres around those limits.
  • 15 per cent within Coimbatore, Erode and Tiruppur Corporation limits.
  • 10 per cent within the listed Corporation limits of Trichy, Madurai, Salem, Tirunelveli, Thoothukudi, Vellore, Thanjavur, Dindigul, Nagercoil, Hosur and Avadi.
  • 5 per cent within all municipal limits.
  • 10 per cent for buildings in the Nilgiris, Kodaikanal and Yercaud hills.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Are these rates used to value the land as well as the building?

No. The schedule states that the plinth area valuation excludes the cost of land.

When are the 2025-2026 plinth area rates applicable?

The approved rates operate from 16 August 2025 to 15 August 2026.

Will a building in Chennai have an additional amount added to the base rate?

Yes. For items I to XV, an extra 20 per cent applies within Chennai Corporation limits and within the 32 kilometre belt around those limits.

What happens if a building item is not covered by the plinth area schedule?

Its rate may be taken from the Common Schedule of Rates for 2025-2026 or from the approved plinth area rates used for rough cost estimates for building schemes for that year.