G.O.(Ms).No.07, Guidelines for Removal of Unauthorised Development
The Housing and Urban Development [UD4(1)] Department issued G.O.(Ms).No.07 dated 10 January 2023, setting guidelines for enforcement against unauthorised developments under the Tamil Nadu Town and Country Planning Act, 1971 and the Tamil Nadu Town and Country Planning (Removal of Unauthorised Development) Rules, 2022. It lays down how records must be checked, inspections conducted, notices served, deviations recorded, and buildings locked and sealed.
What the guidelines govern
G.O.(Ms).No.07 dated 10 January 2023 provides procedures for planning authorities and local bodies dealing with buildings constructed without planning permission, in deviation from an approved plan, or after permission has been revoked. It affects building owners, occupiers, developers and enforcement officials.
The guidelines follow the Madras High Court observation that an enforcement authority which sanctioned a plan should not routinely ask an alleged violator to provide its copy.
Checking records and inspecting buildings
The enforcement authority must first check its database to confirm whether approval was issued. If approval exists, the authority must retrieve the approved plan from its own records and take it to the inspection.
If the database shows no approval, or the authority does not have the approved plan, the owner must be given an opportunity to produce available records. Key steps are:
- Form I must allow at least 3 days for producing documents.
- Form II must give not less than 7 days notice of inspection.
- The authorised officer must inspect the building in the owner's presence within 15 days.
- The inspecting officer must prepare an inspection report and identify the appropriate enforcement action.
The officer issuing Forms I and II cannot be below the designated planning, architectural, supervisory or engineering level specified for the relevant authority or local body.
Notices for different violations
G.O.(Ms).No.07 dated 10 January 2023 prescribes different forms according to the condition of the development:
- Form III applies where development was completed without planning permission or after permission was revoked. It must give at least 30 days to restore the land and is served on the owner or occupier.
- Form IV applies to completed construction that departs from an approved plan. It must give at least 30 days to restore compliance and is served on the owner or occupier.
- Form V is a stop work notice for ongoing work without approval or contrary to approval. It must be served on both the owner and developer.
- Form VI requires removal of work continued after receipt of Form V. It must give at least 7 days and be served on both the owner and developer.
Forms IV and V must tabulate approved details, site conditions and deviations, including additional floors.
Locking, sealing and monitoring
The Head or Chief Executive Officer of the authority or local body must issue Form VII for locking and sealing. Locked premises must be kept in safe custody, reported in writing to the jurisdictional police station and checked frequently for unauthorised occupation. Broken or tampered seals must also be reported to the police.
Officials must monitor notice deadlines without delay. A register recording inspections and notices must be submitted to the Head or Chief Executive Officer once every 3 months.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
Can the planning authority ask me to produce my approved building plan?
The authority must first check its own database and records. If no approval is shown or its copy is unavailable, Form I may give the building owner at least 3 days to produce available records, including an approved plan.
What happens if construction continues after a stop work notice?
Form VI may require removal of the portion constructed after receipt of the Form V stop work notice. Form VI must give at least 7 days and must be served on both the owner and developer.
Who can issue a lock and seal order?
The lock and seal order in Form VII must be issued by the Head or Chief Executive Officer of the authority or local body.
Will occupiers receive notice for an unauthorised or deviated building?
Forms III and IV are issued to the building owner for rectification and to all occupiers of the unauthorised or deviated building for discontinuance of use.