G.O. (D) No. 95, Underground Sewerage Scheme for Karaikudi and Pollachi Municipalities, 2015
The Municipal Administration and Water Supply (MA.3) Department issued Government Order (D) Number 95 on 11 February 2015 to amend Government Order (D) Number 531 dated 24 December 2014. The amendment names the Tamil Nadu Water Supply and Drainage Board as the implementing agency for the underground sewerage schemes in Karaikudi Municipality and Pollachi Municipality.
What the order does
Government Order (D) Number 95 of the Municipal Administration and Water Supply (MA.3) Department amends the earlier administrative sanction for underground sewerage schemes in Karaikudi Municipality and Pollachi Municipality. The amendment was made after the Director of Municipal Administration asked the Government to identify the authority responsible for executing the works.
The amendment inserts a new paragraph 11 into Government Order (D) Number 531 dated 24 December 2014. The existing paragraph 11 is consequently renumbered as paragraph 12.
Implementing authority
The Tamil Nadu Water Supply and Drainage Board is designated as the implementing agency for executing the underground sewerage schemes in both municipalities.
Key points are:
- The Tamil Nadu Water Supply and Drainage Board will execute the underground sewerage scheme in Karaikudi Municipality.
- The Tamil Nadu Water Supply and Drainage Board will also execute the underground sewerage scheme in Pollachi Municipality.
- The schemes form part of Sustainable Municipal Infrastructure Financing in Tamil Nadu Phase II Part I.
- The change clarifies responsibility for implementation. It does not provide a new administrative sanction amount.
Earlier administrative sanction
Government Order (D) Number 531 had already granted administrative sanction for the two sewerage schemes. The source records:
- Karaikudi Municipality received administrative sanction for Rs.112.53 crore, with operation and maintenance cost of Rs.113.32 lakh.
- Pollachi Municipality received administrative sanction for Rs.109.62 crore, with operation and maintenance cost of Rs.221.12 lakh.
Government Order (D) Number 95 leaves those stated amounts in place and adds the identity of the implementing agency.
Who is affected
Government Order (D) Number 95 directly concerns the Tamil Nadu Water Supply and Drainage Board, the Director of Municipal Administration, Karaikudi Municipality and Pollachi Municipality. It is relevant to residents, property owners and professionals seeking to identify the public authority responsible for executing the sewerage works.
The document contains no provision changing land ownership, title, classification, planning permission or individual property rights. Its stated purpose is to assign responsibility for implementing municipal underground sewerage infrastructure.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
Who will carry out the underground sewerage works in Karaikudi and Pollachi?
The Tamil Nadu Water Supply and Drainage Board is the implementing agency for the underground sewerage schemes in both municipalities.
Does Government Order (D) Number 95 approve new project funding?
No new sanction amount is stated. The document amends Government Order (D) Number 531 to identify the implementing agency.
What funding was already sanctioned for the two municipalities?
The source records Rs.112.53 crore with operation and maintenance cost of Rs.113.32 lakh for Karaikudi Municipality, and Rs.109.62 crore with operation and maintenance cost of Rs.221.12 lakh for Pollachi Municipality.
Does the document change my land title or property rights?
The document contains no provision changing land ownership, title, classification, planning permission or individual property rights. It deals with responsibility for executing municipal sewerage schemes.