G.O.Ms.No.5, Hill Area Development Programme Energy Conservation Sector, 2015
The Planning, Development and Special Initiatives (TC II) Department issued G.O.Ms.No.5 on 20 January 2015, sanctioning Rs.150.00 lakhs for energy conservation schemes in the Nilgiris District during 2014 to 2015 under the Hill Area Development Programme. The funding covers solar lighting and solar water heating projects, and the document sets requirements for fund release, implementation, monitoring and reporting.
What the document does
G.O.Ms.No.5 of the Planning, Development and Special Initiatives (TC II) Department, dated 20 January 2015, approves expenditure of Rs.150.00 lakhs for energy conservation schemes in the Nilgiris District during 2014 to 2015. The Planning Commission, Government of India, had approved the same outlay under the Hill Area Development Programme.
The document is a funding and implementation approval for public energy projects. It contains no provision changing private ownership, granting land rights or altering land classification.
Schemes and funding
The sanctioned works are:
- Rs.28.000 lakhs for solar cluster home lighting systems and solar street lights in unelectrified tribal hamlets, to conserve kerosene and provide household lighting.
- Rs.49.000 lakhs for solar street lights in tribal areas where electric street lights could not be provided.
- Rs.34.000 lakhs for solar water heating systems in government tribal residential schools, Adi Dravida welfare institutions, other government schools, college hostels, Anganwadi centres, noon meal centres, government hospitals, primary health centres and health sub centres.
- Rs.39.000 lakhs for solar street lights in other habitations and specified government institutions where electric street lights could not be provided.
Of the total allocation, Rs.110.000 lakhs is identified for priority watershed areas and Rs.40.000 lakhs for other watershed areas.
Implementation and oversight
The Collector of Nilgiris is authorised to draw the sanctioned amount and deposit it in the District Rural Development Agency Savings Bank Account for payment to executing agencies.
The Project Director, Hill Area Development Programme, Udhagamandalam must oversee the works, follow existing procedures and, wherever possible, use specifications approved by the Ministry of New and Renewable Energy and the Tamil Nadu Energy Development Agency rate contract.
Key controls include:
- Detailed estimates and a Project Report must be available before money is disbursed.
- Funds may be transferred after receipt of a work order specifying the commencement date.
- Final payment may be released only after a completion certificate is received.
- Relevant Project Reports should cover baseline surveys, beneficiary identification, land use, watershed features and projected impacts.
- Projects requiring public participation in site selection should include photographic evidence and supporting remote sensing maps.
- Completion reports must include photographs, use and impact information, beneficiary feedback and financial details.
The Tamil Nadu Energy Development Agency and the Project Director must submit monthly progress reports to the Government by the 15th of every month.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
Does G.O.Ms.No.5 change ownership or land classification in the Nilgiris?
No such change is provided in the document. It sanctions and regulates expenditure for solar lighting and solar water heating schemes.
Which areas receive the sanctioned funding?
The schemes are for the Nilgiris District. The allocation identifies Rs.110.000 lakhs for priority watershed areas and Rs.40.000 lakhs for other watershed areas.
Can project funds be released without a detailed estimate?
No. Detailed estimates and a Project Report must be available for each work before disbursement, and copies must be submitted in advance for monitoring.
Who is responsible for monitoring the energy conservation works?
The Project Director, Hill Area Development Programme, Udhagamandalam oversees implementation and inspections. The Secretary to Government, Energy Department watches implementation, while the Tamil Nadu Energy Development Agency and the Project Director submit monthly progress reports.