G.O. (D) No. 205, Cauvery Delta Desilting Works, 2019

The Public Works (W2) Department issued Government Order G.O. (D) No. 205 on 18 July 2019, granting administrative sanction of Rs. 6095.40 lakh for 281 Cauvery Delta desilting and related watercourse works. The works cover rivers, odai, surplus courses, irrigation channels, supply channels and drains in nine districts, with the aim of ensuring free flow of water.

Category
Revenue and land administration
Effective
1 January 2019
Pages
53
Status
In force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What the document does

Government Order G.O. (D) No. 205, issued by the Public Works (W2) Department on 18 July 2019, approves funding and administrative sanction for watercourse maintenance in the Cauvery Delta. The approved amount is Rs. 6095.40 lakh for 281 works during 2019-20.

The works involve desilting, regrading and removing shoals from:

  • Rivers and odai.
  • Surplus courses.
  • Irrigation channels and their branches.
  • Supply channels feeding tanks.
  • Drains.

The proposal explains that accumulated silt and shoals were hindering efficient water supply. The Engineer-in-Chief, Water Resources Department and Chief Engineer (General), Public Works Department, was authorised to incur the approved expenditure and directed to complete the works before September or October 2019 to ensure free flow of water.

Areas covered

Government Order G.O. (D) No. 205 covers works in:

  • Namakkal.
  • Erode.
  • Karur.
  • Trichy.
  • Ariyalur.
  • Thanjavur.
  • Thiruvarur.
  • Nagapattinam.
  • Pudukkottai.

The annexure identifies individual works by district, taluk, watercourse, estimated amount and length. Examples include shoal removal in the Raja, Kumarapalayam and Mohanur channels in Namakkal, work on the Pugalur Canal in Erode, work on the South Bank Canal and other channels in Karur, and desilting of sluice channels and drains in Srirangam Taluk of Trichy.

Who may be affected

Government agencies responsible for irrigation channels, drains and related water resources are directly affected because the document authorises expenditure and implementation. Farmers, landowners and occupiers near the listed watercourses may see maintenance activity intended to improve water flow.

Government Order G.O. (D) No. 205 does not set out any transfer of private land, change of land classification, building restriction, compensation process or property fee. A buyer or owner should use the annexed work list to check whether a nearby river, canal, channel or drain was included, rather than treating the document as a record of title or ownership.

Key approval details

  • The revised proposal sought Rs. 6206.90 lakh for 314 works.
  • The Government approved Rs. 6095.40 lakh for 281 works.
  • The approved expenditure was assigned to the stated capital outlay account for medium irrigation and water resources management.
  • The Finance Department concurred on 18 July 2019.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Does G.O. (D) No. 205 change the ownership or classification of my land?

No ownership transfer or land classification change is set out in the document. It approves funding and administrative sanction for desilting and related watercourse works.

Which districts are covered by the approved works?

The works cover Namakkal, Erode, Karur, Trichy, Ariyalur, Thanjavur, Thiruvarur, Nagapattinam and Pudukkottai districts.

How many works were approved and for what amount?

The Public Works (W2) Department approved 281 works for Rs. 6095.40 lakh.

How can I check whether a canal or drain near my property was included?

The annexure lists works by district, taluk, name of work, estimated amount and length. Check the relevant district and taluk entries for the nearby river, canal, channel or drain.