official guidance

G. O. (Ms). No.224, Modernisation of Melmangalam supply channel, 2011

The Public Works (W1) Department of the Government of Tamil Nadu issued Government Order (Ms.) No. 224, dated 1 November 2011, granting administrative sanction of Rs.4 crore to modernise the Melmangalam supply channel in Melmangalam village, Periyakulam Taluk, Theni District. The project is funded through Rs.380 lakh in NABARD loan assistance under RIDF XVII and a Rs.20 lakh state share.

Category
Revenue and land administration
Effective
1 January 2011
Pages
2
Status
In force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

Purpose

Government Order (Ms.) No. 224, dated 1 November 2011, from the Public Works (W1) Department approves government expenditure for modernising the Melmangalam supply channel in Melmangalam village, Periyakulam Taluk, Theni District. The estimate was submitted by the Chief Engineer (Plan Formulation), Water Resources Department, using the schedule of rates for 2010-2011 and including provision for escalation during 2011-2012.

Who it affects

Government Order (Ms.) No. 224 directly concerns the Water Resources Department, the Public Works (W1) Department, the Theni District administration, the relevant accounting and treasury authorities, and NABARD. Residents, landowners and agricultural users in Melmangalam may be interested because the approved work concerns the village supply channel, but the document does not describe individual properties or private land rights.

Key provisions

The Public Works (W1) Department approved the following arrangements:

  • Administrative sanction of Rs.4,00,00,000 for modernisation of the Melmangalam supply channel.
  • NABARD loan assistance of Rs.380 lakh, representing 95 per cent of the project amount.
  • A Tamil Nadu state share of Rs.20 lakh, representing 5 per cent of the project amount.
  • Funding under RIDF XVII, as part of irrigation schemes approved by NABARD.
  • Charging the expenditure to a new account head under Demand No.40.01 for capital outlay on major and medium irrigation schemes.

Budget and administrative process

Government Order (Ms.) No. 224 treats the sanctioned expenditure as an item of New Service requiring approval from the Legislature. Until that approval is obtained, expenditure is to be met initially through an advance from the Contingency Fund, subject to separate orders from the Finance (BG-I) Department.

The Engineer-in-Chief, Water Resources Department, must submit the required proposal for the Contingency Fund advance and draft explanatory notes for including the expenditure in the Supplementary Estimates for 2011-2012. The Engineer-in-Chief is also designated as the estimating, reconciling and controlling authority for the new account sub-head. The relevant Pay and Accounts Officer and Treasury Officers are directed to open that sub-head in their accounts.

Relevance to property records

Government Order (Ms.) No. 224 is an administrative and financial approval for an irrigation project. It does not record a land acquisition, transfer ownership, alter a patta, approve a change of land use or identify any private survey number.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Does Government Order (Ms.) No. 224 change my patta or property ownership?

No change to pattas or ownership is stated. The document grants administrative and financial approval for modernising the Melmangalam supply channel.

How much money was approved for the Melmangalam supply channel?

The Public Works (W1) Department approved Rs.4 crore. NABARD loan assistance accounts for Rs.380 lakh, and the state share is Rs.20 lakh.

Where is the approved irrigation work located?

The work concerns the Melmangalam supply channel in Melmangalam village, Periyakulam Taluk, Theni District.

Does the document say when the modernisation work will be completed?

No completion date or construction timetable is stated. The document deals with administrative sanction, funding and accounting arrangements.