G.O.(D).No.44, Release of Balance State Share under PMGSY Phase VIII, 2017

The Rural Development and Panchayat Raj (CGS.2) Department issued G.O.(D).No.44 dated 6 February 2017, authorising the release of Rs.3.97 crore to the Director of Rural Development and Panchayat Raj, Chennai, as the balance State share for rural road works under Pradhan Mantri Gram Sadak Yojana Phase VIII (2012-13) and Bharat Nirman Phase III. The document concerns government funding for rural roads and does not state any change to private land ownership, pattas or land classification.

Category
Revenue and land administration
Effective
1 January 2017
Pages
3
Status
In force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

Purpose

G.O.(D).No.44 dated 6 February 2017 was issued by the Rural Development and Panchayat Raj (CGS.2) Department. It releases the remaining State contribution for new rural road connectivity and road upgrades under Pradhan Mantri Gram Sadak Yojana Phase VIII (2012-13) and Bharat Nirman Phase III.

The road works were to be executed by the Rural Development and Panchayat Raj Department and the Highways and Minor Ports Department.

Financial background

G.O.(D).No.44 records that the original administrative sanction covered road works costing Rs.1130.10 crore and maintenance costing Rs.66.84 crore. The original project funding included:

  • Government of India share of Rs.1021.15 crore.
  • State share of Rs.108.95 crore.
  • Allocation of Rs.95.25 crore to the Rural Development and Panchayat Raj Department.
  • Allocation of Rs.13.70 crore to the Highways and Minor Ports Department.

Three road works were later removed from the approved list because they had been taken up under another scheme. After their deletion, the project cost was recalculated as Rs.1128.74 crore, comprising a Central share of Rs.1019.87 crore and a State contribution of Rs.108.87 crore.

The document also records that the Government of India changed the funding pattern for ongoing schemes from 100 per cent Central funding to a 60:40 Central and State pattern from 1 April 2015.

Amount released and administration

G.O.(D).No.44 accepts the request of the Director of Rural Development and Panchayat Raj to release Rs.3.97 crore instead of Rs.4.05 crore. The reduction reflects the deletion of the three road works and the recalculated State contribution.

Key directions are:

  • Rs.3.97 crore is released as the balance State share.
  • The Director of Rural Development and Panchayat Raj, Chennai, may draw and disburse the amount.
  • Expenditure is assigned to the stated capital outlay account for rural road and bridge works under Pradhan Mantri Gram Sadak Yojana and Bharat Nirman.
  • The Finance Department concurred with the release.

Relevance to property owners

G.O.(D).No.44 is a financial sanction for government rural road works. It does not identify individual roads, villages, survey numbers or private properties, and it contains no provision changing ownership, patta records or land classification. Any effect on a particular property cannot be determined from this document alone.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Does G.O.(D).No.44 change my patta or land ownership?

No such change is stated. G.O.(D).No.44 deals with the release of the State share for rural road works and contains no provision concerning pattas or private ownership.

How much money was released under G.O.(D).No.44?

The Rural Development and Panchayat Raj (CGS.2) Department authorised the release of Rs.3.97 crore as the balance State share.

Why was Rs.3.97 crore released instead of Rs.4.05 crore?

Three road works were deleted because they had been taken up under another scheme. The State contribution was therefore recalculated from Rs.108.95 crore to Rs.108.87 crore.

Can I find out from G.O.(D).No.44 whether my property is affected by a road project?