TNRERA Authority order (Form M)
I.A.No.74/2024 in C.No.60/2023
Parties involved
- Complainant
- BPCL Staff Residence Welfare Society
- Respondent
- Lakshmi Royal Home Constructions and Others
Hearings of this complaint (listed on 32 days)
-
28 Sep 2026 Case diary, TN RERA Authority
C. No. 60/2023
Counsel for Complainant present. Counsel for Respondents-1, 3, 4 and 7 present. Respondent-2 called absent. Counsel for Respondent-5 present Respondents-6 & 8 called absent Counsel for proposed 9th Respondent present. Counsel for Respondents-10 to 15 present Respondent-16 called absent Counsel for Respondents-17 to 19 called absent during calling hours and appeared belatedly. The Authority heard the parties. During last hearing the Authority directed the Complainant and the Respondents to file Terms of Reference for the appointment of Auditor for Forensic Audit and Engineer to arrive at the co...
-
28 Sep 2026 Cause list, TN RERA Authority
C.No.60/2023 listed for hearing.
-
5 Aug 2026 Case diary, TN RERA Authority
C. No. 60/2023
The Complainant Counsel present. The Counsel for Respondents-1, 3, 4 and 7 present. The Counsel for Respondent-2 present. The Counsel for Respondent-5 present The Respondents-6 & 8 called absent. The Counsel for 9th respondent present. Counsel for Respondents-10 to 15 present Counsel for Respondent-16 present Respondents-17 to 19 called absent. All the parties made their detailed submissions. The Authority directs all the Respondents to file their counter in respect of impleading petitions filed by the Complainant Association within two weeks before the Registry and serve copy to other sides....
Next: 28 Sep 2026, for further adjudication
-
5 Aug 2026 Cause list, TN RERA Authority
C.No.60/2023 listed for hearing.
-
28 Jul 2026 Cause list, TN RERA Authority
C.No.60/2023 listed for hearing.
-
7 Jul 2026 Case diary, TN RERA Authority
C. No. 60/2023
The counsel for the Complainant present The counsel for the Respondents-1, 3, 4 and 7 present The counsel for the Respondent-2 present The counsel for the 5th Respondent present. The Respondents-6 & 8 called absent. The counsel for the impleaded 9th Respondent present. The counsel for Respondents-10 to 16 present. The Respondents-17 to 19 called absent. The counsel for the Respondents-1, 3, 4 & 7 filed revised proposal to complete the project by serving copy to the counsel for the Complainant and other Respondents. They have also filed additional typed set of documents wherein they have listed...
Next: 28 Jul 2026, for further adjudication
-
7 Jul 2026 Cause list, TN RERA Authority
C.No.60/2023 listed for hearing (P.M.).
-
2 Jun 2026 Case diary, TN RERA Authority
C. No. 60/2023
The counsel for the Complainant present The counsel for Respondents-1, 3, 4 and 7 present The counsel M/s. K.S. Theerthaa for Respondent-2 present and undertook to file vakalat. The counsel for the 5th Respondent present. The Respondents-6 & 8 called absent. The impleaded Respondent-9 called absent. The counsel for Respondents-10 to 16 present. The Respondents-17 to 19 called absent. The counsel for the Respondents-1, 3, 4 & 7 presented a proposal regarding the completion of the project. The Respondent has indicated the amount required for completing the project including the liabilities in th...
Next: 7 Jul 2026, for further adjudication
-
2 Jun 2026 Cause list, TN RERA Authority
C.No.60/2023 listed for hearing (P.M.).
-
28 Apr 2026 Cause list, TN RERA Authority
C.No.60/2023 listed for hearing.
Next: 2 Jun 2026, reposted, as the list's notice says
-
7 Apr 2026 Case diary, TN RERA Authority
C. No. 60/2023
The Counsel for the Complainant present The Counsel for Respondents-1, 3, 4 and 7 present The Counsel for Respondent-2 present The Respondents-6 & 8 present. The Counsel for the 5th Respondent present. The Counsel for impleaded Respondent-9 present. The Counsel for Respondents-10 to 16 present. The Counsel for Respondents-17 to 19 present. During last hearing, the Authority had set up a Committee of Advocates to discuss various issues relating to this project and find a mutually agreeable solution. The said Committee met on 07.03.2026, but could not arrive at any decision as can be seen from t...
Next: 28 Apr 2026, for further adjudication
-
7 Apr 2026 Cause list, TN RERA Authority
C.No.60/2023 listed for hearing (P.M.).
From the cause lists and case diaries TN RERA publishes, matched to this order by its complaint number.
Project details
Project "Bharat Residency" at Vanagaram Village, Ambathur Taluk, Thiruvallur District.
Order document
Loading PDF viewer...
Related cases
- 71/2020 C.Jothi v. Sri Lakshmi Builders Authority 03 Sep 2026
- I.A. No.2/2026 in CCP No.26/2023 1) Sylvanus Builders and Developers Ltd., and 2) Pacifica (C... v. 1) K. Subbulakshmi and 2) S. Jeyaraj Adjudicating 25 Feb 2026
- E.P. No.16/2025 in CCP No.57/2023 P. Vijay Neelakandan (Deceased) and Others v. 1) C. Sridevi and 2) S. Vijayalakshmi Adjudicating 18 Nov 2025
- E.P.No.5/2025 in C.No.77/2023 Venkatakrishnan Ramaswamy v. Green Avenue Homes & Gardens Authority 16 Oct 2026
Need Complete Property Verification?
Get ownership details, EC records, FMB, zone checks, geo-insights & AI analysis - all in one place
Ask the records, or walk the map.
LandLens One answers from Tamil Nadu land law itself, cited to the page, then acts on the registers. One Map lights them up on the parcel. Your history stays in one place across both.
YOU APPROVE ANY SPEND
*Some tools are free of charge, but you need a credit balance to use LandLens One and One Map chat.