TNRERA Authority order (Form M)
I.A.No.75/2025 in C.No.21/2025
Parties involved
- Complainant
- Sabarinath
- Respondent
- 1) Sobha Westhill Owners Association, 2) Sobha Limited (formerly Sobha Developers Limited), 3) Jagadish Nangineni and 4) Ravi PNC Menon, Chairman, Sobha Limited (formerly Sobha Developers Limited)
Hearings of this complaint (listed on 13 days)
-
26 Oct 2026 Case diary, TN RERA Authority
C.No.021/2025
Counsel for Complainant Association present Counsel for the Respondents present The Authority heard the arguments by both sides and posted to 23.11.2026 for further arguments. In the meantime, both the parties are directed to file written submission of arguments within two weeks before the Registry, if not filed already.
Next: 23 Nov 2026, for further arguments
-
26 Oct 2026 Cause list, TN RERA Authority
C.No.21/2025 (Arguments) listed for hearing (Arguments).
-
14 Oct 2026 Case diary, TN RERA Authority
C.No.021/2025
Counsel for Complainant Association present Counsel for the Respondents present Both the counsels argued the matter in detail. The Authority heard the parties and needs clarification from the Respondent whether the land gifted is for public purpose or OSR land and the details of infrastructures put up in the lands gifted to Localbody. This needs to be clarified by the Respondent during next hearing. Posted to 26.10.2026 for further arguments.
Next: 26 Oct 2026, for further arguments
-
14 Oct 2026 Cause list, TN RERA Authority
C.No.21/2025 listed for hearing at 3.00 P.M..
-
24 Aug 2026 Case diary, TN RERA Authority
C.No.021/2025
Counsel for Complainant Association present and filed additional typed set of documentsalready made their oral submissions. Counsel for the Respondents present and filed typed set documents and two citations in support of his arguments. Regarding allegation that the common amenities are constructed in the land gifted for road and parks, the Respondents denied and stated that the common amenities are provided within the approved layout area and there is no violation. A copy of the approved drawing and approval letters are furnished in the typed set documents. Regarding the allegation that OSR l...
Next: 14 Oct 2026, for further adjudication
-
24 Aug 2026 Cause list, TN RERA Authority
C.No.21/2025 (Arguments) listed for hearing at 3.00 P.M. (Arguments).
-
17 Aug 2026 Case diary, TN RERA Authority
C.No.021/2025
Counsel for Complainant present and submitted that the Respondent has constructed the bore wells in the land gifted to the Corporation. The compound wall constructed by the Respondent has been demolished by the Corporation as encroachment. In the land gifted for the purpose of road and parks, Respondent has constructed common amenities. The STP has been constructed in the plot No.12 the ownership of the plot lies with the Respondent. Counsel for the Respondent specifically alleged that they have not encroached the OSR land and all the infrastructure are provided in the common areas and sought...
Next: 24 Aug 2026, for arguments by the Respondent finally
-
17 Aug 2026 Cause list, TN RERA Authority
C.No.21/2025 (Arguments) listed for hearing at 3.00 P.M. (Arguments).
-
8 Jul 2026 Case diary, TN RERA Authority
C.No.021/2025
The counsel for Complainant present The counsel for Respondents present and sought time to argue the matter since their senior counsel is not available today to argue the matter. The Authority posted the matter to 17.08.2026 for arguments finally. If the Respondents do not argue the matter during next hearing, the opportunity to argue the matter will be closed.
Next: 17 Aug 2026, for arguments finally
-
8 Jul 2026 Cause list, TN RERA Authority
C.No.21/2025 (Arguments) listed for hearing at 3.00 P.M. (Arguments).
-
15 Jun 2026 Case diary, TN RERA Authority
021/2025
The counsel for Complainant present and filed Memo requesting to remove the name of the first counsel for the Complainant M/s. Guruprasad from the counsels for the Complainant and the memo is recorded. The counsel for Respondents-1 to 4 present and filed adoption memo in respect of Respondents-2 to 4 adopting the counter filed by the Respondent-1 and served copy to the counsel for the Complainant. Posted to 08.07.2026 for arguments finally.
Next: 8 Jul 2026, for arguments finally
-
15 Jun 2026 Cause list, TN RERA Authority
C.No.21/2025 (Arguments) listed for hearing at 3.00 P.M. (Arguments).
From the cause lists and case diaries TN RERA publishes, matched to this order by its complaint number.
Project details
Project "Sobha Westhill Phase-I, II & III" at Coimbatore North, Coimbatore.
Order document
Loading PDF viewer...
Related cases
- 41/2023 1) V. Velmurugan and 2) Pramila Velmurugan v. Sobha Ltd., (formerly Sobha Developers Ltd.,) Adjudicating 19 Nov 2024
- 92/2023 1) Ramasamy Rajasekar and 2) Jothi Rajasekar v. Sobha Ltd., (formerly Sobha Developers Ltd.,) Adjudicating 01 Oct 2024
- 91/2023 1) T.V. Panchapakesan and 2) P. Banumathi v. Sobha Ltd., (formerly Sobha Developers Ltd.,) Adjudicating 01 Oct 2024
- RCP No.94/2025 G. Ramamalini v. Cyber City Housing Private Limited SMB 21 Oct 2026
Need Complete Property Verification?
Get ownership details, EC records, FMB, zone checks, geo-insights & AI analysis - all in one place
Ask the records, or walk the map.
LandLens One answers from Tamil Nadu land law itself, cited to the page, then acts on the registers. One Map lights them up on the parcel. Your history stays in one place across both.
YOU APPROVE ANY SPEND
*Some tools are free of charge, but you need a credit balance to use LandLens One and One Map chat.