G.O.Ms.No.153, Construction of Additional Four Suites for Circuit House at Cuddalore, 2008
The Government of Tamil Nadu, Public Works (Y2) Department, issued G.O.Ms.No.153 dated 21 May 2008, granting administrative sanction of Rs.48.00 lakhs to construct four additional suites at the Circuit House in Cuddalore. The work is within the existing Circuit House campus and the order does not change land ownership, land use or property rights.
What the document authorises
The Government of Tamil Nadu, Public Works (Y2) Department, issued G.O.Ms.No.153 dated 21 May 2008 to approve construction of four additional suites at the Circuit House in Cuddalore. Administrative sanction is granted for Rs.48.00 lakhs under the Part II Schemes for 2008-2009.
The Chief Engineer (Buildings) proposed the work because visiting V.V.I.Ps and senior officers travelling to Chidambaram, Sirkali and Puducherry frequently preferred to stay at Cuddalore. The existing Circuit House, constructed during 1980-1981, had four suites, and its accommodation was considered inadequate in both quality and availability.
Land and property relevance
G.O.Ms.No.153 dated 21 May 2008 states that sufficient land for the additional construction is available within the existing Circuit House campus. It does not provide for acquiring private land or changing the ownership, classification or permitted use of surrounding property.
The document mainly affects the Public Works Department officials responsible for approving, funding and carrying out the building work. It does not impose any requirement on private property buyers or owners in Cuddalore.
Key provisions
- Administrative sanction is granted for Rs.48.00 lakhs for four additional suites at the Circuit House in Cuddalore.
- The proposal was approved by the Standing Finance Committee under the Part II Schemes for 2008-2009.
- Expenditure for the scheme during 2008-2009 is stated as Rs.36.00 lakhs.
- P.S. charges, contingencies and unforeseen expenses together must not exceed 2.5 per cent of the cost of the work.
- The estimate was prepared using schedule rates for 2008-2009 and is approved.
- The Chief Engineer (Buildings) is authorised to incur expenditure under existing procedures.
- The expenditure is assigned to the specified capital outlay account for Public Works office buildings and major works.
- The Finance Department concurred through U.O.No.156/DS(AR)/PW-I/2008-1 dated 2 May 2008.
Practical effect
G.O.Ms.No.153 dated 21 May 2008 is a project and spending approval for government accommodation. A person checking private land records or purchasing property near the Circuit House would not obtain any change in title or development rights from this document.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
Does G.O.Ms.No.153 acquire any private land in Cuddalore?
No. The document states that sufficient land is available within the existing Circuit House campus and does not authorise acquisition of private land.
How many new suites were approved for the Cuddalore Circuit House?
The Government of Tamil Nadu approved construction of four additional suites.
What amount was sanctioned for the construction?
Administrative sanction was granted for Rs.48.00 lakhs. The expenditure stated for 2008-2009 was Rs.36.00 lakhs.
Does this document affect my property rights or land use?
The document does not change private property rights or land use. It approves construction and expenditure within the existing Circuit House campus.