G.O. (Ms.) No. 01, Amendment to rule 45 of Tamil Nadu Combined Development and Building Rules, 2019, 2023
The Housing and Urban Development [UD4(1)] Department issued G.O. (Ms.) No. 01 dated 2 January 2023 to amend rule 45 of the Tamil Nadu Combined Development and Building Rules, 2019. The amendments set minimum separation requirements for Wind Electricity Generators, prohibit their erection within 500 metres of a dwelling unit, and require micro-siting plans and specifications to be certified by the Tamil Nadu Generation and Distribution Corporation Limited.
What the document changes
G.O. (Ms.) No. 01 dated 2 January 2023, issued by the Housing and Urban Development [UD4(1)] Department, amends rule 45 of the Tamil Nadu Combined Development and Building Rules, 2019. The appended notification was directed to be published in the Tamil Nadu Government Gazette Extraordinary dated 2 January 2023.
The amendment deals specifically with the location, separation and certification requirements for a Wind Electricity Generator, also described as a WEG.
Required distance from roads and other features
The amended rule requires a minimum distance between a Wind Electricity Generator and each of the following:
- Public roads.
- Railway tracks.
- Highways.
- High voltage electric lines.
- Buildings.
- Public institutions.
The minimum distance is calculated by adding:
- The tower height or hub height, measured in metres.
- Half the blade or rotor diameter, measured in metres.
- An additional 5 metres.
The required separation therefore depends on the measurements of the particular Wind Electricity Generator.
Protection for dwelling units
The amended rule states that a Wind Electricity Generator must not be erected within 500 metres of any dwelling unit. This provision is directly relevant to owners, occupiers and buyers of residential property near a proposed wind energy installation, as well as developers and operators selecting a location for a generator.
The source text does not describe how the 500 metre distance is to be measured or provide exceptions to the restriction.
Certification of plans
The amended rule requires the plan showing the micro-siting of Wind Electricity Generators within a site to be certified by the Tamil Nadu Generation and Distribution Corporation Limited.
The certification requirement also covers the specifications concerning:
- Development.
- Installation.
- Erection.
- Operation.
Property owners, project developers and professionals dealing with a proposed Wind Electricity Generator site should therefore check both the applicable separation distances and whether the required plan and specifications have been certified by the Tamil Nadu Generation and Distribution Corporation Limited.
This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.
Common questions
Can a Wind Electricity Generator be erected within 500 metres of my house?
No. The amendment states that a Wind Electricity Generator must not be erected within 500 metres of any dwelling unit.
How is the minimum distance from a public road or building calculated?
The minimum distance is the tower or hub height, plus half the blade or rotor diameter, plus 5 metres. All measurements used in the calculation are in metres.
Does the distance requirement also apply near railway tracks and high voltage electric lines?
Yes. The listed features include public roads, railway tracks, highways, high voltage electric lines, buildings and public institutions.
Who must certify the micro-siting plan for a Wind Electricity Generator?
The Tamil Nadu Generation and Distribution Corporation Limited must certify the micro-siting plan and the specifications concerning development, installation, erection and operation.