TNRERA Completion Intimation Forms for Buildings and Layouts

The Tamil Nadu Real Estate Regulatory Authority issued Proceedings No. TNRERA/A3/1840/2026-2, dated 16 June 2026, prescribing separate forms for promoters to intimate completion of registered building and layout projects. The forms require project, completion, designated bank account and audit information, supported by technical records, photographs and a scrutiny fee of Rs. 5000. Separate evidence requirements apply to buildings and layouts.

Category
RERA
Effective
1 January 2026
Pages
11
Status
In force
Open the source document The official copy, as published. Opens in a new tab.
Source document Preview loads as you scroll

What it governs

The Tamil Nadu Real Estate Regulatory Authority Proceedings No. TNRERA/A3/1840/2026-2, dated 16 June 2026, provides two completion intimation formats:

  • Form-I for a real estate building project.
  • Form-II for a real estate layout project.

The promoter must identify the project, land, registration details and completion date. The promoter must declare that the project was completed according to planning approval and conditions imposed by No Objection Certificate agencies or departments.

Financial declarations

Both completion forms require details of the project’s three designated accounts:

  • RERA Designated Collection Account, 100 percent.
  • RERA Designated Separate Account, 70 percent.
  • RERA Designated Transaction Account, 30 percent.

The promoter must declare that 70 percent of the money collected from allottees or buyers was deposited in the designated separate account and used for project development. Audited project accounts, bank statements for all three accounts for the last one year, and a Chartered Accountant’s certificate showing collections, expenditure and balances must be submitted.

Building projects

Form-I requires the number of residential and commercial units, total land extent, total floor space index area and completion certificate details. Supporting documents include:

  • Form-4A certified by the architect.
  • Form-4B structural stability certificate from a registered structural engineer.
  • Planning approval, approved plan and registration documents.
  • Completion certificate from the competent authority, or from the architect or engineer where a planning authority certificate is not mandatory.
  • Latest quarterly progress report and Form-7 annual statement of accounts.
  • Geo-tagged photographs of blocks, towers, common amenities and the entire project.
  • Details of pending complaints before the Tamil Nadu Real Estate Regulatory Authority or other courts.

A separate promoter declaration must provide evidence that water supply, sewerage, electricity and lifts are available and functional. It must also confirm that promised common amenities have been provided and are functional.

Layout projects

Form-II requires promoters to identify infrastructure or development works that were pending at registration and conditions imposed by No Objection Certificate agencies. Supporting evidence includes Form-5, approved plans bearing the local body seal, security deposit details where applicable, and geo-tagged photographs showing infrastructure such as roads, bridges, culverts, parks and storm water drains.

Both forms specify a scrutiny fee of Rs. 5000.

This summary is generated from the source document to help you find what is relevant. The PDF above is authoritative. For advice on your own property, use LandLens One or speak to a qualified professional.

Common questions

Who files the completion intimation with TNRERA?

The promoter of the registered real estate project files the completion intimation. Form-I applies to building projects and Form-II applies to layout projects.

Does a completed building project need a structural stability certificate?

Yes. The building completion documents include Form-4B, a structural stability certificate certified by a registered structural engineer.

What bank records must a promoter submit?

The promoter must submit bank statements for all three RERA designated accounts for the last one year. A Chartered Accountant’s audited certificate showing funds collected, expenditure incurred and account balances is also required.

Are photographs required for a completion report?

Yes. Building and layout completion reports require good quality, geo-tagged photographs. Building photographs must cover blocks, interiors, exteriors, common amenities and the overall project, while layout photographs must show the entire project and infrastructure works.